CFG pile, pipe pile embankment reinforcement system and construction method thereof
A construction method and technology of tubular piles, applied in roads, sheet pile walls, foundation structure engineering, etc., can solve the problems of high embankment filling specifications, difficult to degrade concrete pile heads, long construction period, etc., to achieve filling and compaction The effect of low requirements, small scope of base reinforcement, and short construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Example Embodiment
[0028] CFG pile, pipe pile embankment reinforcement system construction method embodiment 1: in the following order
[0029] 1. Construction of supporting structure bottom pipe piles or 1 row of pipe piles or CFG piles on each side;
[0030] 2. Laying steel bars, standing formwork, pouring concrete for supporting structure, and reserve cup openings for electrochemical support and prestressed anchor cable channels in the concrete for supporting structure;
[0031] 3. The soil is compacted and filled to the bottom of the prestressed raft to construct the pile foundation construction platform;
[0032] 4. Construction of 4 rows of pipe piles or CFG piles in the middle of the embankment;
[0033] 5. Clean the prestressed raft foundation, and clean the prestressed raft foundation trough on the middle pipe pile or the upper pile foundation construction platform of the middle CFG pile;
[0034] 6. Pre-stressed anchor cables through the raft, reinforcement of the raft, and pre-stressed an...
Example Embodiment
[0044] CFG pile, pipe pile embankment reinforcement system construction method embodiment 2: in the following order
[0045] 1. Construction of supporting structure bottom pipe piles or 2 rows of pipe piles or CFG piles on both sides;
[0046] 2. Laying steel bars, standing formwork, pouring concrete for supporting structure, and reserve cup openings for electrochemical support and prestressed anchor cable channels in the concrete for supporting structure;
[0047] 3. The soil is compacted and filled to the bottom of the prestressed raft to construct the pile foundation construction platform;
[0048] 4. Construction of 12 rows of pipe piles or CFG piles in the middle of the embankment;
[0049] 5. Clean the prestressed raft foundation, and clean the prestressed raft foundation trough on the middle pipe pile or the upper pile foundation construction platform of the middle CFG pile;
[0050] 6. Pre-stressed anchor cables through the raft, and lay raft steel bars and tensile pre-str...
Example Embodiment
[0060] CFG pile, pipe pile embankment reinforcement system construction method embodiment 3: in the following order
[0061] 1. Construction of supporting structure bottom pipe piles or 3 rows of pipe piles or CFG piles on both sides;
[0062] 2. Laying steel bars, standing formwork, pouring concrete for supporting structure, and reserve cup openings for electrochemical support and prestressed anchor cable channels in the concrete for supporting structure;
[0063] 3. The soil is compacted and filled to the bottom of the prestressed raft to construct the pile foundation construction platform;
[0064] 4. Construct 20 rows of pipe piles or CFG piles in the middle of the embankment;
[0065] 5. Clean the prestressed raft foundation, and clean the prestressed raft foundation trough on the middle pipe pile or the upper pile foundation construction platform of the middle CFG pile;
[0066] 6. Pre-stressed anchor cables through the raft, and lay raft steel bars and tensile pre-stressed ...
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology