Multi-working face circulating development driving production organization method
A production organization and multi-operation technology, which is applied in ground mining, earth square drilling, underground mining, etc., to achieve the effects of improving equipment efficiency, small mutual interference, and improving safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0024] Example 1: A large-scale underground mine adopts the joint development of vertical shafts and slopes, and the sub-level caving method without pillars. The designed annual comprehensive production capacity of mining and dressing is 4 million tons. In order to maintain the continuous and stable mining production of the mine, there must be sufficient production preparations in the stope. For this reason, the mine needs to excavate 8000m of mining roadways every year (an average monthly excavation of about 670m). Boomer281 full-hydraulic drilling jumbo is used for tunneling and rock drilling, explosive charging jumbo or manual blasting is used for tunneling, and TORO301D diesel scraper is used for tunneling and slag removal. The labor organization adopts three shifts. When excavating the roadway, the centralized excavation production organization method with the area as the unit is adopted. There are four excavation teams, and each excavation team has three operation areas. ...
Embodiment 2
[0025]Example 2: A large-scale underground mine adopts the joint development of adit and slope road, and the sub-level caving method with bottom pillars for mining, and the designed annual comprehensive production capacity of mining and dressing is 1.5 million tons. In order to maintain the continuous and stable mining production of the mine, there must be sufficient production preparations in the stope. For this reason, the mine needs to excavate 4000m of mining roadway every year (an average monthly excavation of about 330m). Boomer281 full-hydraulic drilling jumbo is used for tunneling and rock drilling, explosive charging jumbo or manual blasting is used for tunneling, and TORO301D diesel scraper is used for tunneling and slag removal. The labor organization adopts three shifts. When excavating the roadway, the centralized excavation production organization method with the area as the unit is adopted, and the excavation team is divided into three groups: excavation rock dri...