TBM tunneling and secondary lining synchronous construction method at mucking of continuous belt conveyor and trolley
A secondary lining and simultaneous construction technology, which is applied in shaft lining, tunnel lining, earthwork drilling and mining, etc., can solve the problems of inability to realize simultaneous construction of secondary mold lining and long construction period, and solve the problems of long exposure time of surrounding rock, The effect of shortening the tunnel construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] (1) Assemble the TBM, which is basically completed. After entering the preparation hole, continue to improve and debug the whole machine. At the same time, assemble 2 synchronous lining trolleys (1# and 2# trolleys) at the TBM assembly site. If conditions permit, 2 trolleys Assemble at the same time, otherwise assemble 1# and 2# trolleys in sequence.
[0030] (2) After the trolleys are assembled, enter the preparation hole and drive to the area close to the TBM. If the two trolleys are assembled at the same time, they will enter the hole at the same time, otherwise they will enter in sequence.
[0031] (3) Install the continuous belt conveyor and pass through the two lining trolleys to make it a complete system and reach the state of normal operation.
[0032] (4) The TBM and the two trolleys step forward at the same time, and extend the continuous belt conveyor while stepping until it reaches the tunnel surface. If the distance of the preparatory hole is long, the tur...