Method for connecting concrete pile and bearing platform
A technology of concrete pile and connection method, which is applied in construction, infrastructure engineering and other directions, can solve the problems of difficult control of construction quality of core-filled concrete, influence of core-filled concrete on uplift quality, and inability to clean the inner wall mud, so as to avoid engineering safety. Accidents, reducing engineering safety hazards, and improving the effect of construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] The present invention will be further described below in conjunction with accompanying drawing and specific embodiment:
[0026] like figure 1 , 2 , 3, 4, 5 and 6: a method for connecting a concrete pile to a cap, comprising the following steps:
[0027] First, after the pile foundation construction is completed, measure the actual elevation of the top of the concrete pile 1;
[0028] When the actual elevation of the pile top of the concrete pile 1 is equal to or lower than the design elevation, a plurality of connecting steel sleeves 7 are installed on the tension screw holes 9 of the end plate 6 of the concrete pile 1, and then the screw thread connected with the foundation cap 2 The steel bar 8 is installed on the connecting steel sleeve 7 to realize the connection between the end plate 6 and the threaded steel bar 8, and then ordinary concrete is poured on the foundation cap 2 connected with the concrete pile 1, so that the concrete pile 1 and the foundation cap ...