Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof

A bridge crane and hoisting technology, which is applied in the direction of walking bridge cranes, cranes, transportation and packaging, etc., can solve the problems of increasing the number of hoisting and high-altitude work time, dispatching a large amount of investment in equipment roofing, and affecting the progress of plant structure installation. , to achieve the effect of reducing the risk of high-altitude operation, reducing the risk of high-altitude operation, and reducing the risk of hoisting

Inactive Publication Date: 2013-07-03
CHINA FIRST METALLURGICAL GROUP
View PDF5 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The traditional installation method of large and medium-sized bridge cranes is to use large hydraulic cranes (or crawler cranes) for single-machine hoisting or double-machine hoisting. When hoisting, the site is required to be flat and wide, which is convenient for the crane station, and the safety risk of hoisting is high.
At the same time, limited by the lifting height and lifting weight, the weight of a single piece lifted by the bridge crane is limited, which increases the number of hoisting and high-altitude operation time. In addition, the roof structure needs to be removed to meet the hoisting requirements, which affects the installation progress of the plant structure.
Since large-scale hydraulic cranes (or crawler cranes) are used for hoisting, a wide station parking space is required, and large equipment transported to the site cannot be placed in a centralized manner. It is necessary to hoist one piece and transport one piece at a time, which increases a lot of transportation work
The deployment and use of large-scale hoisting cranes, the unloading of equipment, and the demolition of roofs all require a lot of investment and increase costs.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0048] as attached figure 1 As shown, the beam crane method provided by the present invention is a method for installing a bridge crane, which is a method for setting a load-bearing beam and utilizing a winch to install a bridge crane. The steps include lifting the load-bearing beam, winches, and setting of lifting points; Production; arrangement of pulley blocks and wire ropes; ground assembly of bridge cranes; hoisting of bridge crane bridges; hoisting of main and auxiliary trolleys of bridge cranes; installation of wire ropes and hooks of bridge cranes. Specifically, follow the steps below:

[0049] Step 1. Setting of load-bearing beam, winch and lifting point:

[0050] (1) The load-bearing beams for hoisting use roof beams. If the factory roof is designed in the form of trusses, before installing the roof, select a truss connected to the factory building columns to be changed to a load-bearing beam design. The load-bearing beam meets the requirements of 120t lifting cap...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a method for installing a bridge crane using load-supporting roof beams for hoisting and usage thereof. The invention is characterized in that: hoisting points are arranged on roof beams of a workshop, components of the bridge crane are assembled on the ground on site, and hoists and specified suspenders are used for hoisting the bridge crane; the method mainly comprises the steps of arranging of load-supporting beams for hoisting, hoists and hoisting points, fabrication of the specified suspenders, arranging of assembly pulleys and wire ropes, assembly of the bridge crane on the ground, hoisting of bridge stands of the bridge crane, hoisting of main and assistant trolleys of the bridge crane and installation of the wire ropes and the suspenders. According to the invention, site requirements are low, finished roofing of the workshop does not need to be dismounted, no giant crane is utilized, and facilities purchased and suspenders fabricated at a time can be used repeatedly, thereby saving cost; lifting and suspending with two cranes are avoided, thereby reducing safety risks; components are assembled in place on the ground and hoisted at a time, thereby improving working efficiency and abating risks in high altitude construction; time for actual hoisting is short and operationality is strong; the method is applicable to installation of large and medium-sized bridge cranes without being influenced by sites or hoisting height.

Description

technical field [0001] The invention relates to an installation method of a bridge crane, in particular to a method for installing a large and medium-sized bridge crane by using a load-bearing beam in cooperation with a winch and the application of the method. Background technique [0002] The traditional installation method of large and medium-sized bridge cranes is to use large hydraulic cranes (or crawler cranes) for single-machine hoisting or double-machine hoisting. During hoisting, the site is required to be flat and wide, which is convenient for the crane station, and the safety risk of hoisting is high. At the same time, limited by the lifting height and lifting weight, the weight of a single piece lifted by the bridge crane is limited, which increases the number of hoisting and high-altitude operations. In addition, the roof structure needs to be removed to meet the hoisting requirements, which affects the installation progress of the plant structure. Since large-sc...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): B66C17/04
Inventor 周汉生张仁强易湧湧
Owner CHINA FIRST METALLURGICAL GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products