Method for constructing foundation slab embedded with concrete supports

A foundation floor and construction method technology, which is applied in the direction of foundation structure engineering, excavation, artificial island, etc., can solve the problems of too long cantilever end at the lower part of the enclosure wall, unfavorable foundation pit deformation control, and slow construction speed, etc. The effects of foundation pit deformation control, avoidance of demolition and slag removal operations, and acceleration of construction speed

Active Publication Date: 2012-06-13
SHANGHAI CONSTR NO 1 GRP
View PDF6 Cites 9 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The technical problem to be solved by the present invention is to provide a construction method for the embedded foundation floor with concrete support, so as to solve the problem that the cantilever end of the lower part of the enclosure wall is too long in the construction of the current ultra-thick foundation floor, which is not conducive to the deformation control of the foundation pit and is not conducive to material saving. , slow construction speed and other issues

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for constructing foundation slab embedded with concrete supports
  • Method for constructing foundation slab embedded with concrete supports
  • Method for constructing foundation slab embedded with concrete supports

Examples

Experimental program
Comparison scheme
Effect test

specific Embodiment

[0026] A specific embodiment, such as the construction of the foundation slab of a shipping plaza, due to the ultra-thick foundation slab, the thickness of the main building area slab is 5.0m, the continuous pouring volume of concrete is large, and the bottom support, that is, the fourth concrete support is located at the elevation of the slab Inside. If the conventional construction method is adopted, the cushion layer is poured first, then the fourth support is removed, and the bottom plate is finally poured. Then the unsupported cantilever end of the lower part of the retaining wall is 6.35m long, which is disadvantageous to the deformation control of the foundation pit and the construction speed is slow.

[0027] Such as Figure 1~4 As shown, the steps of the construction method of the concrete support embedded foundation base plate of the present invention are as follows:

[0028] (1) Dig the soil to the fourth support surface 2, tie the support steel bars, and pre-embed the ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a method for constructing a foundation slab embedded with concrete supports, which comprises the following steps of: digging to the bottommost support surface of soil body, binding support reinforcing steel bars, and embedding foundation slab joint bars; arranging an isolating layer between surrounding purlines and a building envelope; arranging a water stopping structure at a place, which is close to the building envelope, of the support; after binding of the support reinforcing steel bars is finished and pre-embedded parts are embedded, pouring the concretes; after the supports are maintained to the required strength, digging to the bottom of the soil body, pouring plain concretes as a cushion layer, building a bracket for the foundation slab reinforcing steel bars, binding the foundation slab reinforcing steel bars, and connecting a sleeve with the pre-embedded foundation slab reinforcing steel bars on the supports; and pouring foundation slab concretes so as to embed the concrete supports in the foundation slab. The method disclosed by the invention can effectively reduce the length of the end, which has no support cantilever, of the lower part of a retaining wall, thereby preventing demolishing and slag removal works of the bottommost support, facilitating deformation control of foundation pits as well as material saving, and accelerating construction speed of the foundation slab.

Description

Technical field [0001] The invention belongs to the technical field of building underground engineering, and relates to a construction method of a foundation slab, in particular to a construction method of an ultra-thick foundation slab, in particular to a construction method of a concrete support embedded in the foundation slab at the lowest level of the foundation slab. Background technique [0002] The conventional method of foundation slab construction is to remove the support after the slab is poured. When the foundation floor is too thick, the bottom support is located within the elevation of the floor. According to conventional practices, after the cushion is poured, the bottom support needs to be removed before pouring the floor. At this time, because the unsupported cantilever end of the lower part of the enclosure wall is too long, it is not conducive to the deformation control of the foundation pit. In addition, the dismantling and cleaning of supports are not conduci...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D29/045E02D17/02E02D31/02
Inventor 黄玉林朱毅敏陈军赖文周臻全朱刚
Owner SHANGHAI CONSTR NO 1 GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products