Construction process for large-aperture brick and concrete reverse hanging well
A construction technology and large-diameter technology, applied in infrastructure engineering, excavation, construction, etc., can solve problems such as lack of unified planning, difficulty in acceptance, and inability to guarantee construction quality, and achieve the effect of ensuring construction quality.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0017] A construction technique for large-diameter brick-concrete upside-down wells,
[0018] a. Choose the location of the working pit
[0019] The following factors should be fully considered:
[0020] ① Facilitate the construction of pipeline docking work surface and well chamber;
[0021] ②It is convenient for foundation pit excavation and earthwork transportation;
[0022] ③ It is easy to take protection and safe construction measures for above-ground and underground buildings and various pipe networks;
[0023] ④Convenient transportation;
[0024] b. Excavation of working pit
[0025] ① According to the positioning line, excavate the soil evenly and symmetrically along the lower part of the well wall, and the depth of each excavation shall not exceed 500 mm. After the surrounding circle is built, the middle part of the earth shall be excavated, and the construction shall be carried out symmetrically downward in this order. The masonry of the upper part is control...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com