Construction method of edge top arch and bottom arch of concrete pouring tunnel
A construction method, concrete technology, applied in tunnels, tunnel linings, earthwork drilling and mining, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0062] For tunnels with circular sections that require concrete lining construction, the pouring sequence of the bottom arch within the range of 120° below the center of the circular cavern is firstly constructed, and then the side arches are constructed; , the side and roof arch adopts the construction process of integral mobile steel pipe scaffolding equipped with steel formwork; the length of the mobile scaffold is 12m, and two sections of flexible connection are used, and the entire turning section is replaced by a smooth transition of several broken line sections;
[0063] First, the construction method of pouring the bottom arch of the tunnel:
[0064] a. Rock surface cleaning, foundation acceptance:
[0065] Remove the sundries, soil, loose blocks and concrete spraying layer within the concrete pouring range, and rinse them with high-pressure water; before the bottom arch reinforcement is installed, a number of Φ25mm inserts are installed, and the row spacing between in...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com