Construction method of long spiral cast-in-situ bored pile

A technology of long auger drilling and construction method, which is applied in the direction of sheet pile wall, foundation structure engineering, building, etc. It can solve the problems of no site, collapsed hole, excessive thickness of reduced diameter sediment, etc., and achieve good pile quality and good surrounding environment The effect of small impact and short construction period

Inactive Publication Date: 2012-08-08
CHINA RAILWAY HI TECH IND CORP LTD +2
View PDF2 Cites 18 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] In the construction of subways in cities, it is inevitable to construct bored piles as enclosure structures or uplift piles, load-bearing piles, etc. Traditionally, rotary drills and rotary drills are used in the construction, and hole collapse, diameter shrinkage, and excessive sediment are unavoidable. and other quality problems, and a large amount of mud wall protection is required in the process, and mud production, circulation, and disposal sites are required. Construction of subways in cities often has no site for the above-mentioned processes.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020] A construction method of a long spiral bored pile includes the following steps:

[0021] The first step, leveling the site and measuring and laying out

[0022] After leveling the construction site, measure and set the line, and measure the ground elevation in the site to determine the buried depth of the pile top; according to the structural edge relationship of the design drawing, measure the starting and ending pile positions and related control points of the corner and conduct a review ; If there is a long auger rig that cannot be constructed in the pit or the location of the measurement point is the construction area, and the long-term existence or normal use of the measurement point cannot be guaranteed, a protective pile must be made to avoid damage to the measurement point during the construction process.

[0023] The second step, the drilling rig is in place

[0024] After the rig is in place, check the tower guide rods with the front and back and left and right vertic...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a long spiral cast-in-situ bored pile. When used for constructing the cast-in-situ bored pile in an underground station, the method has the advantages of good pile forming quality, short construction period, high effect, no need of mud preparing, circulating and disposal sites and other places, small influence on the surrounding environment, good pile forming quality and the like, and can satisfy the characteristics and requirements, such as high construction environment protection requirement, of the underground station. In addition, the construction method disclosed by the invention is also applicable to various soils, such as clays, silts and miscellaneous fills, and can be used for constructing cast-in-situ bored piles under complicated geological conditions which are liable to generate collapse, hole shrinkage and the like, such as soft soil, drift sand formation, sand-pebble layers, and high underground water levels.

Description

Technical field [0001] The invention relates to a construction method of a long spiral bored pile, in particular to a construction method of a long spiral bored pile in a subway station or other complicated geological conditions. Background technique [0002] In the construction of subways in cities, it is inevitable to construct bored piles as enclosing structures or uplift piles, load-bearing piles, etc. Traditionally, rotary drills and rotary drills are used to inevitably produce hole collapse, diameter reduction, and excessive sedimentation thickness. In addition, the process requires a large amount of mud to protect the wall, and requires mud production, recycling, and disposal sites. There is often no site for the above process to build subways in cities. Summary of the invention [0003] The purpose of the present invention is to provide a bored pile construction method that does not require mud preparation, circulation, disposal, etc., and can meet the characteristics of h...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/36
Inventor 段绍和卿三惠陈强艾兵兵
Owner CHINA RAILWAY HI TECH IND CORP LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products