Overall heating automatic welding process of spud leg main coil of offshore drilling platform and special tool of overall heating automatic welding process

An ocean drilling platform, the overall heating technology, applied in the direction of welding equipment, welding equipment, auxiliary welding equipment, etc., can solve the problems of low welding efficiency, heavy load, difficult manufacturing, etc., to achieve the improvement of production efficiency and welding quality, practical production The effect of the production method

Active Publication Date: 2012-10-03
SHANGHAI ZHENHUA HEAVY IND GRP NANTONG TRANSMISSION MACHINERY
View PDF6 Cites 22 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In the offshore engineering equipment industry, the technical level of the drilling platform is the highest. The main coil of the offshore platform leg is the key component of the jack-up offshore drilling platform. Its structure is as follows: figure 1 , 2 , 3, mainly includes the rack 1 in the middle and the semicircular chord 2 on both sides of the rack 1, the chord 2 and the rack 1 are welded and fixed, the product has a large load bearing, high dimensional accuracy requirements, and difficult welding characteristics, difficult to manufacture
[0003] At present, in the manufacture of traditional pile leg main coils in China, manual electrode arc welding is mostly used for welding the chords and racks, which has low welding efficiency, high labor intensity for welders, high technical requirements, difficult control of welding accuracy, and poor working environment. Disadvantages such as high production costs

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Overall heating automatic welding process of spud leg main coil of offshore drilling platform and special tool of overall heating automatic welding process
  • Overall heating automatic welding process of spud leg main coil of offshore drilling platform and special tool of overall heating automatic welding process
  • Overall heating automatic welding process of spud leg main coil of offshore drilling platform and special tool of overall heating automatic welding process

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0025] Embodiment 1: Welding the main spiral tube of the pile leg with a rack thickness of 127mm and a chord wall thickness of 38mm.

[0026] Put the racks and chords to be welded into the electric furnace for a preheating, the preheating temperature is 150-200°C, and the whole is heated through. Then use special tooling to position the rack and the chords on both sides, and use flux-cored wire gas shielded welding for root welding. Two people are used to weld symmetrically and in the same direction. The welding temperature is 150-230°C and the welding speed is 430-456mm / min. Properly grind the bottom weld seam, conduct thermal magnetic particle inspection after grinding, and enter the next process after passing the inspection. The racks and chords are placed in the electric furnace for secondary preheating, the preheating temperature is 150-200°C, and the whole is thoroughly heated. Then carry out secondary welding, use automatic submerged arc welding to fill and cover the r...

Embodiment 2

[0027] Embodiment 2: Welding the main spinning tube of the pile leg with a rack thickness of 152.4mm and a chord wall thickness of 38mm.

[0028] Put the racks and chords to be welded into the electric furnace for a preheating, the preheating temperature is 170-230°C, and the whole is heated through. Then use special tooling to position the rack and the chords on both sides, and use flux-cored wire gas shielded welding for root welding. Two people are used for symmetrical welding in the same direction. The welding temperature is 150-230°C and the welding speed is 420-440mm / min. Properly grind the bottom weld seam, conduct thermal magnetic particle inspection after grinding, and enter the next process after passing the inspection. The racks and chords are placed in the electric furnace for secondary preheating, the preheating temperature is 170-230°C, and the whole is thoroughly heated. Then carry out secondary welding, use automatic submerged arc welding to fill and cover the...

Embodiment 3

[0029] Embodiment 3: Welding the main spiral pipe of the pile leg with the thickness of the rack being 177.8mm and the wall thickness of the chord pipe being 68-93mm.

[0030] Put the racks and chords to be welded into the electric furnace for a preheating, the preheating temperature is 180-250°C, and the whole is heated through. Then use special tooling to position the rack and the chords on both sides, and use flux-cored wire gas shielded welding for root welding. Two people are used to weld symmetrically and in the same direction. The welding temperature is 150-230°C and the welding speed is 400-430mm / min. Properly grind the bottom weld seam, conduct thermal magnetic particle inspection after grinding, and enter the next process after passing the inspection. The racks and chords are placed in the electric furnace for secondary preheating, the preheating temperature is 180-250°C, and the whole is thoroughly heated. Then carry out secondary welding, use automatic submerged a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
verticalityaaaaaaaaaa
thicknessaaaaaaaaaa
verticalityaaaaaaaaaa
Login to view more

Abstract

The invention relates to an overall heating automatic welding process of a spud leg main coil of an offshore drilling platform and a special tool of the overall heating automatic welding process. The process steps include that after a primary preheating, toothed bars and string pipes on two sides of the toothed bars are positioned and are subjected to a backing weld by the special tool; primary postweld treatment is performed, a backing weld seam is subjected to an appropriate polishing, and then the backing weld seam is subjected to a heat magnetic particle inspection after the polishing; a secondary preheating is performed, and the toothed bars and the string pipes which are subjected to the backing weld are placed in an electric furnace to be preheated again; a secondary welding is performed, an automatic submerged arc welding is utilized to perform filling and capping on the toothed bars and the string pipes which are subjected to the preheating again; and finally heat treatment is performed. By means of a mode of combining a plurality of times of the preheating and welding, and by means of reasonable control of welding temperatures and speeds, the manufacturing of spud leg main coil of the offshore drilling platform is achieved, and design requirements of welding qualities, welding deformation control and postwelding dimensional accuracy are met, so that the production efficiency and welding qualities are remarkably improved, and an effective and practical producing and manufacturing mode is provided for the production of a spud leg main coil of a self-elevating drilling platform.

Description

technical field [0001] The invention relates to a processing technology of the main spiral pipe of the pile leg of the ocean drilling platform, and also relates to a special tool for realizing the overall heating and automatic welding process of the main spiral pipe of the pile leg of the ocean drilling platform. Background technique [0002] With the accelerated pace of ocean development, the development prospects of the ocean engineering equipment industry are getting brighter and brighter. In the offshore engineering equipment industry, the technical level of the drilling platform is the highest. The main coil of the offshore platform leg is the key component of the jack-up offshore drilling platform. Its structure is as follows: figure 1 , 2 , 3, mainly includes the rack 1 in the middle and the semicircular chord 2 on both sides of the rack 1, the chord 2 and the rack 1 are welded and fixed, the product has a large load bearing, high dimensional accuracy requirements, a...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): B23K9/16B23K9/18B23K9/235B23K37/04
Inventor 任志华史伟民宋冰
Owner SHANGHAI ZHENHUA HEAVY IND GRP NANTONG TRANSMISSION MACHINERY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products