Bailey beam support free of buttress in soft foundation and supporting method thereof
A soft foundation and support frame technology, applied in bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of insufficient bearing capacity, increase production cost, increase construction difficulty, etc., achieve uniform stress and save production The effect of shortening cost and construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0033] Example 1, The construction of the 900-ton Beijing-Shanghai high-speed railway uses a 32-meter-long cast-in-place box girder:
[0034] 1) Processing and installation of embedded parts
[0035] according to image 3 The process of the embedded parts provided requires the processing plant to process the geometric steel bars with a welding spacing of 80mm on the steel plate. The welding between the steel bar and the steel plate must be firm, and the length, thickness and fullness of the weld must meet the specification requirements. When constructing the cap, 5 embedded parts are buried in the cap at a distance of 2.5m. During the construction of the pier body, the height of the pier body is 13m, and embedded parts are buried 1.5 meters below the top of the pier, and 5 embedded parts are distributed at a distance of 2.5m.
[0036] 2) Bracket erection
[0037] The number of spiral steel pipes arranged is the same as the number of embedded parts. The embedded parts are ...
Embodiment 2
[0042] Example 2 , to build a 600-ton Beijing-Tianjin high-speed railway, using a 25-meter-long cast-in-place box girder:
[0043] 1) Processing and installation of embedded parts
[0044] according to image 3 The process of the embedded parts provided requires the processing plant to manufacture geometric steel bars with a welding spacing of 100mm on the steel plate. The steel bar and the steel plate must be welded firmly, and the length, thickness and fullness of the weld must meet the specification requirements. When constructing the cap, 3 embedded parts are buried in the cap at a distance of 2.1m. During the construction of the pier body, the height of the pier body is 16m, and the embedded parts are buried 1.5 meters below the top of the pier, and the embedded parts are distributed at 2.3 m intervals.
[0045] 2) Bracket erection
[0046] The number of spiral steel pipes is the same as the number of embedded parts. The spiral steel pipes 2 and the bearing platform an...