Industrial construction methods for buildings

A construction method and building technology, applied in the direction of building structure, building material processing, construction, etc., can solve problems such as difficulty in ensuring high quality, high noise in the mixing process, and easy pollution of the environment, so as to improve efficiency and quality, and speed up Construction progress and the effect of reducing the probability of work-related injuries

Active Publication Date: 2015-11-18
CHINA STATE CONSTR HAILONG TECH CO LTD
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In the wet operation of the construction site, it is necessary to first mix the raw materials into concrete on the construction site through mixers and other equipment. The mixing process is noisy and easy to pollute the environment; moreover, construction through on-site pouring operations requires more mechanical equipment and formwork, etc. Casting and vibrating the various structures of the building, because the construction of the building must require the precise coordination of each structure, making the on-site construction difficult and low in efficiency; in addition, it is easy to produce large errors through on-site fabrication of the structures, and it is difficult to ensure high quality

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Industrial construction methods for buildings
  • Industrial construction methods for buildings
  • Industrial construction methods for buildings

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] refer to Figure 1-3 , the industrial construction method of the building of an embodiment of the present invention, comprises the following steps:

[0032] S1. Prepare a prefabricated part in advance. The prefabricated part includes a prefabricated column 10 , a prefabricated beam, a prefabricated floor 40 and a prefabricated outer wall (not shown), wherein the prefabricated beam includes a main beam 20 and a secondary beam 30 .

[0033] The prefabricated parts are industrially produced according to the requirements, and steel molds are used for production. The prefabricated parts produced are accurate in size and smooth in surface, so that there is no need to do plastering at the construction site. When in use, the prefabricated components are transported to the construction site for installation, which can reduce construction The number of high-altitude workers on site reduces the probability of work-related injuries, and reduces noise and environmental pollution on ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an industrial construction method of a building, which comprises the following steps that S1, a prefabricated member is fabricated in advance; S2, the prefabricated member fabricated in advance is transported to a construction site; S3, a prefabricated column is mounted; S4, a prefabricated beam is mounted; S5, a prefabricated floor slab is mounted; S6, concrete is poured and covered at the top of the prefabricated column, on the prefabricated beam and the prefabricated floor slab, and among the prefabricated column, the prefabricated beam and the prefabricated floor slab; the prefabricated beam and the prefabricated floor slab are connected to form a top slab which is fixed at the top of the prefabricated column; and S7, a prefabricated external wall is mounted: the prefabricated external wall is positioned and mounted on the prefabricated beam and the prefabricated column at the periphery of the top slab. According to the method, each member of the building is industrially produced in advance, then is transported to the construction site for mounting, and finally is connected into a whole by casting joints in place, so that the construction difficulty is reduced, the construction progress is increased, industrial production and mounting are realized, the efficiency and the quality are improved, and the engineering cost and the material consumption are reduced.

Description

technical field [0001] The invention relates to the field of construction, in particular to an industrial construction method of buildings. Background technique [0002] With the continuous development of economy and technology, the traditional cast-in-place operation mode in the construction industry will face a series of challenges: rising labor costs force the construction industry to seek transformation; pollution, noise and other problems caused by wet operations on the construction site are related to green environmental protection violated. In the wet operation of the construction site, it is necessary to first mix the raw materials into concrete on the construction site through mixers and other equipment. The mixing process is noisy and easy to pollute the environment; moreover, construction through on-site pouring operations requires more mechanical equipment and formwork, etc. The various structures of the building are made by pouring and vibrating. Since the cons...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G21/00E04G21/14
Inventor 杨卫东施汉盛张宗军刘新伟薛建新吴丁华周光星
Owner CHINA STATE CONSTR HAILONG TECH CO LTD