A technology of reinforced concrete and prestressed steel bars, applied in structural elements, building components, building structures, etc., can solve the problems of poor construction quality, low input cost, low construction labor, etc., and achieve fast construction progress, low labor intensity, The effect that the construction method is simple
Active Publication Date: 2016-02-10
SCEGC NO 6 CONSTR ENG GRP CO LTD
View PDF4 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
But nowadays, there is no uniform, standardized and specific construction method to follow in the construction of unbonded prestressed cast-in-place reinforced concrete hollow slabs, so the actual construction inevitably has relatively random, irregular construction operations, low construction workers, Low input cost, poor construction quality and many other problems
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0044] Such as figure 1 The construction structure of unbonded prestressed cast-in-place reinforced concrete hollow slab is shown. There are multiple rib beams arranged in parallel inside the unbonded prestressed cast-in-place reinforced concrete hollow slab. The construction structure includes horizontal supports The bottom formwork 1 on the formwork support system, the steel mesh on the lower layer of the slab above the bottom formwork 1, the steel mesh on the upper layer of the slab directly above the steel mesh on the lower layer of the slab, and a plurality of steel meshes arranged on the slab from left to right The inner formwork between the lower steel mesh sheet and the upper layer steel mesh sheet and multiple sets of anti-floating devices that respectively perform upper and lower limit on a plurality of said inner formwork, and a plurality of said inner formwork are rectangular hollow tubes 2 and They are all arranged on the same horizontal plane, and the vertical he...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
PUM
Login to view more
Abstract
The invention discloses an unbonded prestress cast-in-place reinforced concrete hollow slab construction structure and method. The structure comprises a base mold plate, a plate lower-layer rebar mesh sheet, a plate upper-layer rebar mesh sheet, a plurality of inner mold plates, and a plurality of groups of anti-floating devices for limiting the plurality of inner mold plates in an up-down manner, wherein a ribbed beam rebar cage is arranged between two adjacent inner mold plates; a prestress rebar is arranged in each ribbed beam rebar cage in a penetrating manner; ribbed beam stirrups form left and right limiting mechanisms of the inner mold plates; the construction method comprises the following steps: 1, installing the base mold plate, 2, surveying and setting out, 3, bonding the plate lower-layer rebar mesh sheet and the ribbed beam rebar cages, 4, arranging the prestress rebar in the penetrating manner, 5, installing the inner mold plates, 6, performing anti-floating processing, 7, bonding the plate upper-layer rebar mesh sheet, 8, vertically supporting side mold plates, 9, casting concrete, and 10, tensioning the prestress rebar. The method and the structure are reasonable in design, convenient to implement, low in investment cost, high in construction quality, and high in construction speed, and the construction process of a hollow slab can be easily and fast finished with high quality.
Description
technical field [0001] The invention belongs to the technical field of construction of unbonded prestressed cast-in-place slabs, and in particular relates to a construction structure and a construction method of unbonded prestressed cast-in-place reinforced concrete hollow slabs. Background technique [0002] With the continuous demand of the use function, modern buildings tend to have a large space and no indoor beams. The unbonded prestressed cast-in-place reinforced concrete hollow slab structure has the advantages of large span, light weight, heat preservation, sound insulation, free intervals, and large indoor net height. , fast construction and other characteristics, it is on the basis of the original ordinary prefabricated hollow floor structure, the hole diameter is appropriately enlarged, mainly relying on the pre-set unbonded prestressed steel bars to reduce the concrete near the neutral axis, so as to achieve neither reduction The bearing capacity can also reduce ...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.