A 400-ton hoisting pipe-laying ship stinger installation method on water
An installation method and stinger technology, which are applied in the directions of pipe-laying ships, ship components, and ship construction, can solve the problems of insufficient use of safety hammers, and achieve the effect of improving competitiveness and reducing construction costs.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] A method for installing a stinger on a 400-ton lifting pipe-laying vessel on water, comprising the steps of:
[0023] 1) Preparatory work before the water installation of the stinger 1: First, complete the overall assembly of the stinger 1; then, hang the fixed pulley 13, the pin 8, the luffing wire rope 20, the shackle 21, etc.; at the same time, prepare the equipment and facilities including: bearing Floating barge 14, skid 15, weight 17, first chain hoist 6, second chain hoist 25, third chain hoist 28, suspender 27 and wire rope 5; finally, complete the electric motor on the top surface of the hull corridor. The double-drum mooring winch 22 and the luffing winch 23 are debugged, and at the same time record the draft value of the port side of the stern, the draft value of the starboard side of the stern, the distance from the center of the shaft hole of the stern pin seat 10 to the water surface when the ship is stationary;
[0024] Such as figure 1 figure 2 As sho...