A technology of self-anchored suspension bridges and box girders, applied in bridge construction, bridge erection/assembly bridges, etc., can solve problems such as increasing construction risks and costs, increasing complex deviation correction work, reducing the speed of jacking construction, etc., to achieve improved Effects of construction efficiency and quality, reduction of construction period, and reduction of engineering quantity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] Use the above-mentioned construction method to design the pulling erection method of the main tower as the box girder to erect the box girder. The steps are as follows:
[0030] 1) Small-span self-anchored suspension bridges adopt one-way pull (main span ≤ 250m)
[0031] Step 1: Construction of various temporary support structures (temporary piers, welded and assembled platforms, temporary steel pipes, etc.)
[0032] Step 3: The guide beam and several sections of the box girder are assembled, and the traction steel strand is installed to carry out the pulling construction of the box girder;
[0033] Step 3: Continue to assemble the box girder segments, adjust and then carry out pulling construction;
[0034] Step 4: Repeat step 3. When the guide beam penetrates the center line of the main tower, move the end of the steel strand from the anchor at the guide beam to the anchor at the rear part of the box girder section for fixing, and then carry out the pulling construct...