A construction method and construction preparation technology, applied in the direction of basic structure engineering, construction, etc., can solve the problems such as the difficulty of water sealing in the steel sleeve assembly gap, increase the construction cost, and prolong the construction period, so as to optimize the construction plan, reduce manpower, and protect the environment. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0036] The invention relates to a construction method of an underwater cap, the technological principle of which is to realize the manufacture and reinforcement of the underwater cap through processes such as measurement and lofting, foundation pit excavation, underwater mud suction, cushion construction, cap construction and the like.
[0037] This construction method requires the following materials:
[0038] 1. C30 concrete (sand and gravel, cement, fly ash, admixture), talcum powder, grade II steel bar, mixed oil.
[0039] 2. Machinery and equipment: concrete transport vehicles, electric welding machines, pump trucks, cranes, vibratory hammers, excavators, ramming machines, air compressors, high-pressure water guns, total stations, levels, water pumps, steel bending machines, pile drivers, water Lower suction dredge, cooling pipe, conduit, storage hopper.
[0040] This construction method includes the following steps (such as Figure 1 to Figure 4 shown):
[0041] (1) C...