Construction method of TBM-EPB double-mode shield in composite stratum
1. The technology of TBM-EPB and construction method, which is applied in the direction of earth drilling, mining equipment, tunnels, etc., can solve the problems of low self-stability, increased construction cost, safety accidents, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0066] Below in conjunction with accompanying drawing, the present invention is described in detail.
[0067] In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0068] Such as figure 1 and figure 2 As shown, the stratum at the initial excavation place of the shield is a soft rock stratum, and there is a 160-meter-long hard rock stratum behind the soft rock stratum, which is again a soft rock stratum behind the hard rock stratum. The following embodiments adopt the present invention The construction method of its construction, the specific way is as follows:
[0069] (1) Geological survey: carry out geological survey according to the design route, and ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com