Prestressed hollow slab beam end air bag reinforcing construction method
A hollow slab girder and construction method technology, applied in bridge reinforcement, bridge, bridge maintenance, etc., can solve problems such as difficulty in guaranteeing reinforcement effect, reinforcement by enlarging cross-section method, complex construction process, etc., and the quality and progress can be easily controlled and improved The effect of carrying capacity and mature technology
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0015] Refer to the attached drawing, the construction method of prestressed hollow slab beam end airbag reinforcement, opening holes and setting airbags at the beam end, pouring self-leveling concrete around the beam body, increasing the cross-sectional area, and improving the bearing capacity of the bridge. The specific construction method is as follows:
[0016] Use an air compressor and a pneumatic pick to open the manhole 1 on the roof of the hollow slab. The size of the manhole 1 is 0.5m×0.6m. Bending around, adopting rhinestones to set vent holes on both sides, with a diameter of 4cm, arranged near the relatively high end of the two ends of the airbag 4; the two ends of the airbag 4 are reinforced with 24 brick walls 2 in the range of 3m. A horizontal brace is placed every 40cm on the bottom surface, and φ12U-shaped positioning steel bars 3 are arranged above the horizontal brace according to the horizontal position of the airbag. The water gun washes the debris inside ...
PUM