A construction method and a technology of a slurry stop pad, which are applied in wellbore lining, underground chambers, and shaft equipment, etc., can solve the problems of high drainage cost, difficult quality, and long cycle, and achieve convenient construction, controllable quality, and simple process. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0027] Such as Figure 1~2 Among them, an underwater grout stop pad construction device for inclined wells, including multiple grouting guide pipes 1, steel pipes with a diameter of 50-100mm are usually used as the grouting guide pipes 1, the length of a single steel pipe is 6-9M, and the grouting guide pipes 1 are connected by a connecting sleeve 2, the connecting sleeve 2 in this example is a socket type connecting sleeve 2, and the connecting sleeve 2 is socketed on the outer wall of the grouting guide pipe 1.
[0028] A sealing rubber pad 3 is provided at the bottom of the lowest grouting guide pipe 1 to keep water from entering the grouting guide pipe 1 during installation, so as to reduce weight and facilitate installation.
[0029] The outer wall of the grouting guide pipe 1 extending into the water is coated with a floating device 5 . The floating device 5 adopts foamed plastics. So that the grouting guide pipe 1 is always in a floating state during the underwater in...
Embodiment 2
[0034] On the basis of the device in Example 1, a method for using the above-mentioned inclined well underwater grout stop pad device to carry out the grout stop pad construction includes the following steps:
[0035] 1. Install the grouting guide pipe 1, connect multiple grouting guide pipes 1 through the connecting sleeve 2, the connecting sleeve 2 is sleeved on the ends of the two grouting guide pipes 1, and welded with the grouting guide pipe 1 .
[0036] Bind the floating device 5 on the outer wall of the grouting guide pipe 1, and install the sealing rubber pad 3 at the bottom of the lowest grouting guide pipe 1;
[0037] Preferably, a guide head 4 with rounded or chamfered edges is provided at the bottom end of the lowest grouting guide pipe 1 to prevent the bottom end of the grouting guide pipe 1 from colliding with the well pipeline or the well wall and being blocked during installation.
[0038] 2. Set up a drilling rig platform and a grouting platform at the static...