Construction method suitable for emery structural ground of large factory building

A construction method and technology of emery, applied in basic structure engineering, underwater structures, artificial islands, etc., can solve the problems of difficulty in ensuring the quality of the twice-molded ground, and the surface is easily damaged, so as to reduce management costs and operating costs, shorten the Construction period, the effect of ensuring structural strength and quality

Active Publication Date: 2016-02-24
CHINA FIRST METALLURGICAL GROUP
View PDF5 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The technical problem to be solved by the present invention is to provide a method that can not only ensure the quality of the ground but also reduce the construction period, and will not damage the defect that the twice-molded ground is difficult to guarantee the quality of the existing technology, and the one-time molded ground is easy to damage the surface in the later stage of construction. The surface is suitable for the construction method of the emery structure ground of large factory buildings

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method suitable for emery structural ground of large factory building
  • Construction method suitable for emery structural ground of large factory building

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

[0027] Such as figure 1 As shown, the construction method of the emery structure ground suitable for large-scale factory buildings in the embodiment of the present invention includes the following steps:

[0028] S1. Complete the preparatory work before construction, including earthwork excavation, pouring of pile head and cap cushion concrete;

[0029] S2. Carry out measurement and setting-out positioning on the concrete cushion of the cap after pouring. After determining the position of the cap, set a plurality of U-shaped full-length steel bars inside the cap, and perform formwork support and r...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method suitable for an emery structural ground of a large factory building. The construction method comprises the following steps: S1) the preparatory work before construction is finished; S2) the surveying and the positioning are performed on a concrete cushion layer of a bearing platform; multiple U-shaped long reinforcements are arranged in the bearing platform; and the template supporting and the reinforcement treatment are performed on a positioning sideline of the bearing platform; S3) after the template supporting is finished, the concrete casting of the bearing platform and the concrete casting of a structural baseplate cushion layer are performed; S4) a ground upper structure formwork system and a factory building main structure are constructed; and S5) the deburring and the cleaning are performed for the bearing platform; the baseplate reinforcement binding of a two-layer and two-direction structure of an emery structural baseplate is performed; and finally, the casting of concrete at the upper part of the bearing platform and a once-molded emery structural ground is finished. The construction method not only can guarantee the structure strength and quality of the bearing platform, but also can largely shorten the construction period, can guarantee the surface of the bearing platform to be not damaged by later construction, and reduces the management cost and the operation cost.

Description

technical field [0001] The invention relates to the field of building construction, in particular to a construction method suitable for the emery structure ground of large factory buildings. Background technique [0002] At present, there are two construction methods in the large-area corundum ground construction process in the market: one-time forming corundum and secondary corundum construction. The secondary molding diamond structure increases the cost and the molding quality is prone to hollowing, shelling, cracks, uneven color and other phenomena, which affects the use effect. The one-time forming emery structure ground can solve the above problems, improve the quality of the solid structure, shorten the construction period and reduce the cost. However, after the construction of the one-time corundum structure ground is completed, when the superstructure is constructed, the high-support formwork support system of the superstructure will cause damage to the structural g...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D27/14E02D29/05
CPCE02D27/14E02D29/05E02D2250/0023
Inventor 武群山殷滇闫峰杨多娇孟仕豪
Owner CHINA FIRST METALLURGICAL GROUP
Who we serve
  • R&D Engineer