Automatic lifting device for draw shaft video probe
An automatic lifting and video technology, applied in the direction of the hoisting device, the spring mechanism, etc., can solve the problems such as the inability to adjust the moving speed of the video probe, the need for manual lifting of the video probe, and the impact on the quality of the probe shooting, saving manpower and speed. Wide adjustment range and smooth adjustment process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0031] An automatic lifting device for a chute video probe. Such as figure 1 As shown, the automatic lifting device is composed of a support frame 1, a guiding system 2, a frame 3, a well depth positioning system 4, a lifting system 5 and a control system 6.
[0032] The structure of the support frame 1 is as figure 2 As shown: the two ends of the threaded steel pipe 7 are symmetrically installed on the upper end of the "A"-shaped leg 9 through threads, and the tile-shaped steel brackets 8 are symmetrically fixed near the two ends of the threaded steel pipe 7, and the two tile-shaped steel brackets The center line of 8 is perpendicular to the axis of threaded steel pipe 7 and is set horizontally.
[0033] The structure of guidance system 2 is as follows image 3 As shown: the middle of the two first longitudinal steel pipes 10 is symmetrically welded with the first horizontal steel pipe 17 on the left side, and the two first horizontal steel pipes 17 penetrate from the cor...
Embodiment 2
[0043] An automatic lifting device for a chute video probe. Except following technical parameter, all the other are with embodiment 1:
[0044] The length of the first transverse steel pipe 17 is 1 / 4 to 1 / 3 times the length of the second transverse steel pipe 12;
[0045] The distance between the two longitudinal beams 21 is 1.2 to 1.3 times the width of the reel 31 .
[0046] Compared with the prior art, this specific embodiment has the following positive effects:
[0047] 1. No need to build a working platform. When this specific embodiment is used for the detection of the chute shaft wall, the support frame 1 and the frame 3 are respectively placed on both sides of the chute unloading mouth, and the video probe 29 is suspended in the center of the chute through the guide system 2, without building a working platform. Both the support frame 1 and the guide system 2 can be disassembled, and the operation is simple and convenient.
[0048] 2. Save time and effort. In this...