Sheet pile
A steel sheet pile and friction treatment technology, which is applied to sheet pile walls, buildings, and foundation structure engineering, can solve the problems of huge cost, unreasonable, and large friction material installation area, so as to extend the length of piling and improve straightness , the effect of preventing bending
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0110] Since the model experiment (1 / 10 of the actual scale) of the U-shaped steel sheet pile 1 was performed in order to perform the effect verification of this invention, the result is demonstrated below.
[0111] Experiments are carried out by simulating actual construction. A homogeneous sand ground (sand ground) with a depth of 1.5m (actual scale conversion: 15m) was created in a soil box, and a steel sheet pile model that changed the conditions of friction reduction treatment based on hydraulic pressure penetration into the sand ground over the entire length, The penetration resistance ratio (ratio of penetration resistance) and the warp of the steel sheet pile at the time of pile driving under each condition were made into evaluation items, and the experimental result was obtained.
[0112] Experiments were performed by changing the friction-reducing material construction pattern and the construction section length (friction-reducing treatment section length S) of the f...
Embodiment 2
[0140] For the hat-shaped steel sheet pile 5, since the model experiment similar to Example 1 was performed in order to verify the effect of this invention, the result is demonstrated.
[0141] The parameters of the experiment are the friction-reducing material construction pattern and the length S of the friction-reducing treatment interval.
[0142] In the experiment, the entire length of the steel sheet pile was used as the piling length.
[0143] Friction-reducing material construction patterns such as Figures 24A-24E shown. Figures 24A-24E The dimensions in are shown in actual scale. In addition, the plate thickness is 20mm in actual scale.
[0144] The friction-reducing material construction pattern is the same as that of the U-shaped steel sheet pile 1 of Embodiment 1, such as Figures 24A-24E As shown, the following five patterns are formed: Pattern N without friction reducing material 3 (refer to Figure 24A ), from the lower end of the hat-shaped steel sheet p...
Embodiment 3
[0164] Regarding the effect of the present invention, in order to verify the influence of the change in the length of the steel sheet pile, a model experiment (1 / 20 of the actual scale) was performed on the U-shaped steel sheet pile 1, so the results will be described below. .
[0165] Experiments are carried out by simulating actual construction. Create a homogeneous sand foundation with a depth of 2.0m (40m in actual scale conversion) in the soil box, and penetrate into the sand foundation along the entire length based on hydraulic pressure to change the length L to 12m, 24m, and 36m in actual scale conversion. In the steel sheet pile model, the penetration resistance ratio at the time of piling under each condition and the deflection of the steel sheet pile were used as evaluation items, and the experimental results were obtained.
[0166] In addition to the length of the steel sheet pile, an experiment was performed by changing the presence / absence of the friction-reducin...