A technology of prestressed pipeline and construction method, which is applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of staggered orifices, pipeline blockage, easy deformation, etc., and achieves compact device structure, convenient operation, and prevention of deformation. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0027] Segmental beam prestressed pipeline construction methods, such as Figure 1-5 shown, including the following steps,
[0028] A. Install the first notch mold 11 on the template, the other end of the first notch mold 11 is fixed with the first plug 12, the outer side of the first plug 12 is sleeved with the first corrugated pipe 13, and the side wall of the first corrugated pipe 13 Fix with the first positioning steel bar 14, and fix the second plug 121 and the second notch mold 111 at the other end of the first corrugated pipe 13 in sequence, and pouring after the connection is completed to form the matching section 1;
[0029] B. The matching section 1 is removed from the template, and the first notch mold 11, the first plug 12, the second notch mold 111 and the second plug 121 at both ends of the matching section 1 are removed;
[0030] C. Sleeve the plastic pipe 3 inside one end of the matching section 1, and expose half of the plastic pipe 3; the exposed plastic pip...
Embodiment 2
[0035] Segmental beam prestressed pipeline construction methods, such as Figure 1-5 shown, including the following steps,
[0036] A. Install the first notch mold 11 on the template, the other end of the first notch mold 11 is fixed with the first plug 12, the outer side of the first plug 12 is sleeved with the first corrugated pipe 13, and the side wall of the first corrugated pipe 13 Fix with the first positioning steel bar 14, and fix the second plug 121 and the second notch mold 111 at the other end of the first corrugated pipe 13 in sequence, and pouring after the connection is completed to form the matching section 1;
[0037] B. The matching section 1 is removed from the template, and the first notch mold 11, the first plug 12, the second notch mold 111 and the second plug 121 at both ends of the matching section 1 are removed;
[0038] C. Sleeve the plastic pipe 3 inside one end of the matching section 1, and expose half of the plastic pipe 3; the exposed plastic pip...