Long-distance and large-diameter industrial pipeline laying direct burial construction method under self-weight displacement
A technology of industrial pipelines and construction methods, applied in the directions of pipeline laying and maintenance, mechanical equipment, pipes/pipe joints/pipe fittings, etc., can solve the problems of increased construction costs, temporary occupation of land, and high risks, and achieve green construction. , The comprehensive benefit is significant, the effect of improving the efficacy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0016] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0017] like Figure 1 to Figure 4 As shown, the long-distance large-diameter industrial pipeline is laid under the self-weight displacement and directly buried construction method, and the operation is performed according to the following steps,
[0018] a. Draw lines, sprinkle white and gray lines on the original ground after clearing and leveling according to the position of the center line of the pipeline plan design;
[0019] b. Pipeline layout, select the midpoint of the distance between adjacent valve wells on the white gray line, take the center as the star...
PUM
Login to View More Abstract