Construction method for wall connecting element assembly

A construction method and a technology for connecting wall parts, which are applied in the accessories of scaffolding, house structure support, house structure support, etc., can solve the problems of high material and labor costs, hidden danger of water seepage, and high cost

Inactive Publication Date: 2017-01-18
NORTH CHINA METALLURGICAL CONSTR ENG CONSTR +1
View PDF7 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The disadvantage of the pre-embedded steel pipe method is that the cost is high, the disassembly is troublesome, and the post-reserved opening of the masonry must be sealed later, which may cause water seepage
[0004] The post-anchoring method uses at least two expansion anchors, which is extremely troublesome during drilling and construction, and the cost of materials and labor is high
[0005] The hoop column method must wait for the column formwork to be removed before the wall parts can be installed, which seriously causes a delay in the construction period
[0006] The connecting wall rods of the pre-embedded iron plate method need to be connected with the pre-embedded iron plate for welding and cutting when dismantling. There is a fire hazard at the scene of open flames

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for wall connecting element assembly
  • Construction method for wall connecting element assembly
  • Construction method for wall connecting element assembly

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0028] Specific embodiments of the present invention will be described in detail below.

[0029] Such as Figure 1~3 Shown, a kind of construction method of wall-joint component, comprises the following steps:

[0030] (1) Determine the position of the embedded anchor 1 in the beam-slab-column side formwork;

[0031] (2) Put the embedded anchor 1 into the side formwork of the beam-slab-column, and the embedded part of the embedded anchor 1 is at least 70% of the total length;

[0032] (3), pouring concrete in the beam-slab-column side formwork in step (2);

[0033] (4) After the concrete in the side formwork of the beam, slab and column is cured, remove the side form of the beam, slab and column;

[0034] (5), first install a fastening positioning nut 4 at the thread 11 of the protruding rod of the embedded anchor 1, then fasten the connector assembly and the embedded anchor 1 through threaded connection, and finally pass Another fastening positioning nut 4 fixes the posit...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method for wall connecting element assembly comprising following steps: (1) determining the position of a pre-embedded anchor member in beam plate column side mold; (2) putting the pre-embedded anchor member into the beam plate column side mold; (3) pouring concrete into the beam plate column side mold; (4) dismounting the beam plate column side mold after the concrete inside the beam plate column side mold is solidified; (5) installing a fastening positioning screw nut at a thread position of an extending rod of the pre-embedded anchor member, then the connecting element assembly and the pre-embedded anchor member are fastened and connected through threaded connection, and finally, another fastening positioning screw nut is used for fixing the position of the connecting element; (6) one end of a wall connecting rod is fixedly connected with one end of the wall connecting element assembly through a fastener, the wall connecting rod is fixedly connected with at least one framing scaffold through a fastener. The construction method for wall connecting element assembly disclosed in the invention has the following beneficial effects: only the embedded anchor pieces are discarded in the whole wall piece, and the wall connecting element assembly can be reused.

Description

technical field [0001] The invention belongs to the technical field of construction, and in particular relates to a construction method of a wall connecting piece assembly. Background technique [0002] The reliable connection between the external scaffold and the main structure is the key to ensure that the external scaffold does not suffer from instability and damage. At present, the conventional methods of connecting wall parts used in fastener-type steel pipe scaffolding in the construction industry include: pre-embedded steel pipe method, post-anchoring method, hoop column method, and pre-embedded iron plate method. But these methods all have some shortcomings: [0003] The disadvantages of the pre-embedded steel pipe method are that the cost is high, the disassembly is troublesome, and the post-retention hole of the masonry must be sealed in the later stage, which has the hidden danger of water seepage. [0004] The post-anchoring method uses at least two expansion a...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04G5/04
Inventor 张双庆李洪雁
Owner NORTH CHINA METALLURGICAL CONSTR ENG CONSTR