An installation method and rubber membrane technology are applied in the direction of adjustable capacity gas storage tanks, gas/liquid distribution and storage, mechanical equipment, etc., which can solve the problems of high cost, high labor intensity and low efficiency, and ensure that personnel The effects of safety, improving work efficiency and saving labor costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment 1
[0036] Such as Figure 1~3 Shown, a kind of installation method of rubber membrane gas holder comprises the following steps:
[0037] (1) Foundation retesting, laying the bottom plate on the foundation, and then setting the center position on the foundation, thereby expanding the positioning welding outward;
[0038] (2) Lay the piston plate on the bottom plate, then assemble the concrete dam,
[0039] (3) Assemble the cabinet top steel frame 2 on the piston plate, and then lay the welded cabinet top plate 1 on the upper surface of the cabinet top steel frame 2,
[0040] (4) Install 24 first-section columns 4 and the ring beams between the columns, align and fix them, and then assemble the cabinet top steel frame 2 on the ground platform to form several cabinet top trusses; then use tower cranes to install them perpendicular to each other The four trusses of the cabinet are then symmetrically hoisted for other trusses. At the same time, a central platform 3 in contact with t...
specific Embodiment 2
[0051] A method for installing a rubber membrane gas holder, comprising the following steps:
[0052] (1) Foundation retesting, laying the bottom plate on the foundation, and then setting the center position on the foundation, thereby expanding the positioning welding outward;
[0053] (2) Lay the piston plate on the bottom plate, then assemble the concrete dam,
[0054] (3) Assemble the cabinet top steel frame 2 on the piston plate, and then lay the welded cabinet top plate 1 on the upper surface of the cabinet top steel frame 2,
[0055] (4) Install 24 first-section columns 4 and the ring beams between the columns, align and fix them, and then assemble the cabinet top steel frame 2 on the ground platform to form several cabinet top trusses; then use tower cranes to install them perpendicular to each other The eight trusses, and then the other trusses are symmetrically hoisted, and at the same time, the central platform 3 in contact with the ground is installed in the middle...