A production method and an assembled technology are applied in the field of production of large-scale vaulted assembled asphalt storage tanks, which can solve the problems of affecting the installation work of the asphalt storage tank, affecting the normal development of construction during the construction period, and insufficient bolt hole position accuracy, and achieving installation efficiency. And the effect of high pass rate, simple and smooth process and strong reducibility
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0046] The specific embodiment of the present invention will be further described below in conjunction with accompanying drawing:
[0047] Such as figure 1 As shown, the manufacturing method of a large-scale vaulted asphalt storage tank described in the present invention includes two parts: making the tank body 1 and making the tank top 2, wherein:
[0048] 1. Tank production process:
[0049] The tank body 1 is a cylindrical structure enclosed by a plurality of tank wall panels of the same structure and size. The seams between the tank wall panels are overlapped, and the lap joints are connected by high-strength bolts 8; figure 2 As shown, each tank wall panel is composed of a curved panel 3, a tank bottom flange 4, a straight rib 5 and an arc rib 6, wherein the curved panel 3 is composed of multiple steel plates, and its longitudinal direction corresponds to the tank body 1. In the height direction, a liner 7 is provided on one side of the lap joint of the arc panel 3, an...