A Construction Method for Shallow Buried Shield Tunnel Crossing Expressway
A technology for expressways and shield tunnels, applied in tunnels, tunnel linings, earthwork drilling, etc., can solve the lack of construction methods for shallow-buried shield tunnels crossing expressways, endangering personal and property safety, and difficult to apply construction methods, etc. To achieve the effect of reducing the uneven settlement of the tunnel, reducing the difficulty of shield tunneling, and improving the reinforcement effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0053] Such as figure 1 Shown, the present invention comprises the following steps:
[0054] Step 1. Construction preparation:
[0055] Step 101, such as figure 2 As shown, the strata of the tunnel shield area 7 and the reinforcement area 8 above the tunnel shield area 7 are determined; by using the drilling method, it is detected that the tunnel shield area 7 and the reinforcement area 8 are located in the pebble soil layer;
[0056] Step 102, overhaul and maintain the shield machine;
[0057] Step two, pre-grouting construction:
[0058] Step 201, such as figure 2 and image 3 As shown, a plurality of slope grouting holes 1 are provided on the slopes 5 on both sides of the expressway 4, and the slope grouting holes 1 are arranged obliquely toward the bottom of the expressway 4, and a plurality of the slope grouting holes 1 are arranged along the expressway surface. 4 are arranged in rows along the length direction of the slope 5 and arranged in columns along the width ...