A device and construction method for accurately inserting steel bars into plain concrete piles
A plain concrete pile, accurate insertion technology, applied in sheet pile wall, foundation structure engineering, construction and other directions, can solve the problems of inaccurate guarantee, long construction period, bending of steel bars, etc., to achieve the effect of ensuring integrity and reducing resistance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] Such as Figure 1-6 , a device for accurately inserting steel bars into plain concrete piles, it includes a steel bar body 1, the end of the steel bar body 1 is connected with a straight thread sleeve 4 through screw fit, the straight thread sleeve 4 and the steel bar body 1 A steel pipe 3 is sheathed on the outside, and the contact position between the top of the steel pipe 3 and the steel bar body 1 is welded and fixed by a cross iron 2. The outer sheath of the steel pipe 3 is provided with a gear 5, and the top of the steel pipe 3 is connected to the pile driver head.
[0044] Further, the gear 5 is simultaneously engaged with the first gear 6 and the second gear 7 for transmission, and the first gear 6 and the second gear 7 are respectively installed on the other two steel pipes 3 to be inserted outside the steel bar body 1, A gear linkage system is formed to drive the steel pipe 3 to rotate together. Through the gear linkage system, the insertion operation of mult...
Embodiment 2
[0052] The construction method using any one of the steel bar insertion devices includes the following steps:
[0053] Step1: Assemble the device, fix the straight thread sleeve 4 on the bottom external thread 102 of the steel bar 101 through threaded connection, and then set the steel pipe 3 on the outside of the straight thread sleeve 4 and the steel bar body 1;
[0054] Step2: Weld and fix the top of the steel pipe 3 with the steel bar body 1 through the cross iron 2, so that the two are fixedly connected and can transmit torque;
[0055] Step3: Set the gear 5 on the top of the steel pipe 3 to ensure that the gear 5 can transmit the torque to the steel body 1;
[0056]Step4: Connect the top of the steel pipe 3 equipped with the gear 5 with the pile driver, and ensure that the torque of the pile driver can be transmitted to the steel pipe 3;
[0057] Step5: Start the pile driver, insert the steel bar body 1 into the plain concrete pile through the rotation and pressing func...
Embodiment 3
[0061] The concrete manufacturing process of described device is:
[0062] 1. Grind the tip 103 at the end of the length steel bar designed on the drawing, and perform threading treatment near the end of the tip 103, thereby forming the external thread 102;
[0063] 2. Set the straight thread sleeve 4 matching the diameter of the steel bar on the end of the external thread 102 of the steel bar;
[0064] 3. Use a cutting machine to make a cross cut on the end of the steel pipe 3. The depth of the cut is 10cm. Place a steel ring in the cut, weld the port to the steel ring, and polish it into a round mouth. The diameter is 1-3mm, and it is polished, and then the processed steel bar is inserted into the steel pipe;
[0065] 4. When the straight thread sleeve passes through the lower half of the steel pipe, weld and fix the steel pipe and the steel bar with cross irons on the upper part;
[0066] 5. Use the gear linkage system to drive the steel pipe to rotate, and the upper part...