Depressurization and leaking stoppage construction method for high-confined-water post-cast strip
A construction method and technology of post-pouring belts, applied in the field of construction, can solve problems such as failure to fill the pressure drop pipe and new leakage points at the pressure drop pipe, and achieve the effects of fast construction speed, reliable fixation, and simple process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0017] A construction method for pressure-reducing leak plugging of a post-pouring belt under high pressure water, using stainless steel pipe 1, pumping hose 2, flange plate 11, water pump, etc. to drain and depressurize the leakage of post-pouring belt A, and then place the stainless steel pipe 1. Buried directly under the post-casting belt A of the concrete, and sealed the concrete with plugging points and pressure-reducing points.
[0018] Specific steps are as follows:
[0019] 1. At the post-casting belt A where leakage occurs, drill the operation well B with a width of 100mm on each side, drill the inner flat angle on both sides to the position of the structural steel bar, and bury a 50mm diameter and one end at the position where the high-pressure water head occurs. A stainless steel pipe 1 with a flange 11, the surroundings of the stainless steel pipe 1 are tightly sealed with concrete, and if necessary, a waterproof rubber ring is used to seal the stainless steel pipe...
PUM
Login to View More Abstract
Description