Utility tunnel full-length BIM (building information modeling) collaborative design method combining Civil 3D with Revit

A technology of integrated pipe gallery and collaborative design, applied in geometric CAD, calculation, data processing applications, etc., can solve the problem of seldom full-line BIM model establishment, inability to handle the design of pipe gallery intersections, flexible changes and inability to achieve precise control and control. Rapid modeling and other issues to achieve the effect of improving quality and integrity, increasing value, and improving overall investment benefits

Inactive Publication Date: 2017-12-01
中建基础设施勘察设计建设有限公司 +1
View PDF3 Cites 16 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] Due to the limitations of Revit (one of the most widely used BIM software in China), at present, in the design stage of the BIM application of comprehensive utility corridors, engineers mostly only stay in the simulation optimization of node design and comprehensive layout of pipelines, while It is rare to be able to accurately and quickly establish a complete full-line BIM model of the comprehensive utility gallery
The main problem lies in: the actual comprehensive pipe gallery project often presents irregular features in the plane layout and longitudinal section design, that is, the pipe gallery is not an ideal straight line in the plane layout, but a zigzagging and changing broken line and curve; The longitudinal section design will not be a definite slope in a single direction, but will be in the shape of undulations
If Revit is used alone for the BIM design of the comprehensive utility gallery, it cannot achieve precise control and rapid modeling of the flexible changes of broken lines, curves, and multi-slopes shown in the long-distance standard section of the comprehensive utility gallery; if Civil3D is used alone for Comprehensive utility corridor BIM design, which cannot handle the design of utility corridor intersections, entrances and exits, vents and other nodes

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Utility tunnel full-length BIM (building information modeling) collaborative design method combining Civil 3D with Revit

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0055] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0056] The embodiment of the present invention provides a BIM collaborative design method for the whole line of the comprehensive utility gallery by combining Civil3D and Revit, such as figure 1 As shown, first carry out the BIM design of the standard section of the pipe gallery in Civil3D, then carry out the BIM design of the pipe gallery node and complete the node BIM model in Revit, and complete the BIM model of the standard section of the pipe g...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a utility tunnel full-length BIM (building information modeling) collaborative design method combining Civil 3D with Revit. The method comprises: using Civil 3D to draw a tunnel line, generating tunnel vertical section and tunnel standard cross section, and assembling; using the Civil 3D to establish a tunnel road model; using the Civil 3D to extract standard tunnel control line segments from the tunnel line, the tunnel vertical section and the tunnel standard cross section; using Revit to draw a standard utility tunnel segment BIM model in combination with the standard tunnel control line segment; using the Revit to perform tunnel joint BIM design in the standard utility tunnel segment BIM model so as to achieve utility tunnel full-length BIM collaborative design, wherein in Navisworks, the standard utility tunnel segment BIM model and the tunnel joint BIM model are integrated, and interferences between professions and members are collaborated. By fully collaboratively using respective advantages of Civil 3d and Revit, the method herein is capable of establishing the complete utility tunnel full-length BIM model accurately and quickly, thereby arriving at collaborative design.

Description

technical field [0001] The invention relates to the field of BIM design of a comprehensive utility gallery, in particular to a BIM collaborative design method for a full-line comprehensive utility gallery by combining Civil3D and Revit. Background technique [0002] The ideal goal of applying BIM (Building Information Modeling, Building Information Modeling) in the utility tunnel project is to realize the lean management of the whole life cycle of the utility tunnel project based on BIM, especially for the operation and maintenance stage with the longest duration and the highest consumption cost Realize BIM-based intelligent management to reduce operation and maintenance costs, improve operational efficiency, and ultimately maximize project return on investment. In order to realize the intelligent operation and maintenance management of the integrated pipe gallery based on BIM, the most important task is to obtain the complete BIM model of the entire line of the pipe gallery...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06F17/50G06Q10/10G06Q50/08
CPCG06F30/13G06Q10/103G06Q50/08
Inventor 田兆东邢海宁胥方涛徐跃卫程永正闫焱汪莉钟晨宇纪永志于瑞焦剑峰张兆东张子叶刘亚森
Owner 中建基础设施勘察设计建设有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products