Construction method of plastering of building wall surface
A construction method and wall technology, applied in the direction of construction and building structure, can solve the problems of inability to form at one time, plastering bottom cracks, wall cracks, etc., to alleviate the long construction time, reduce construction costs, and absorb slurry powerful effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0068] A construction method for plastering a building wall, said method comprising the following steps:
[0069] (a) Grassroots treatment: treat the grassroots of the building wall to be constructed, and remove the dust, dirt, mortar blocks and other attachments on the wall;
[0070] (b) Prepare the bottom layer slurry: fully mix Portland cement with a strength grade of 42.5 and 801 construction glue at a mass ratio of 3:1 to form the bottom layer slurry;
[0071] (c) Perform plastering of the bottom layer: immerse the plastering and slurry removal device in the bottom layer slurry to stick to the bottom layer slurry, and then, evenly and continuously slap the plastering and slurry removal device full of slurry on the wall, each time The burr height of the prepared slurry is 5mm, and then, after the initial setting of the bottom slurry, use a sprayer to moisturize the wall, and the curing time after moisturizing is 3 days;
[0072] (d) Plastering: After step (c) moisturizing...
Embodiment 2
[0074] A construction method for plastering a building wall, said method comprising the following steps:
[0075] (a) Grassroots treatment: treat the grassroots of the building wall to be constructed, and remove the dust, dirt, mortar blocks and other attachments on the wall;
[0076] (b) Prepare the bottom layer slurry: fully mix Portland cement with a strength grade of 52.5 and 801 construction glue at a mass ratio of 5:1 to form the bottom layer slurry;
[0077] (c) Perform plastering of the bottom layer: immerse the plastering and slurry removal device in the bottom layer slurry to stick to the bottom layer slurry, and then, evenly and continuously slap the plastering and slurry removal device full of slurry on the wall, each time The burr height of the prepared slurry is 7mm, and then, after the initial setting of the bottom slurry, use a sprayer to moisturize the wall, and the curing time after moisturizing is 7 days;
[0078] (d) Plastering: After step (c) moisturizing...
Embodiment 3
[0080] A construction method for plastering a building wall, said method comprising the following steps:
[0081] (a) Grassroots treatment: treat the grassroots of the building wall to be constructed, and remove the dust, dirt, mortar blocks and other attachments on the wall;
[0082] (b) Prepare the bottom layer slurry: fully mix Portland cement with a strength grade of 62.5 and 801 construction glue at a mass ratio of 4:1 to form the bottom layer slurry;
[0083] (c) Perform plastering of the bottom layer: immerse the plastering and slurry removal device in the bottom layer slurry to stick to the bottom layer slurry, and then, evenly and continuously slap the plastering and slurry removal device full of slurry on the wall, each time The burr height of the prepared slurry is 6mm, and then, after the initial setting of the bottom slurry, use a sprayer to moisturize the wall, and the curing time after moisturizing is 4 days;
[0084] (d) Plastering: After step (c) moisturizing...