Construction method for rectangular and variable section hollow pier of bridge
A construction method and hollow pier technology, applied in bridges, bridge parts, bridge materials, etc., can solve the problems of slow formwork turnover, long construction period, and large formwork input, and achieve short construction period, fast formwork turnover, and less formwork input. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0018] The bottom dimension of the outer section of the rectangular variable-section hollow pier (direction along the bridge × cross-bridge direction) is 6.0m×B (B=2.0+H / 80×2, H is the height of the pier column, unit: m), and the top dimension (direction along the bridge × horizontal bridge direction) 6.0m × 2.0m, the chamfer size of the inner box body is 30cm × 30cm, the pier bottom 2.5m and pier top 2.5m are solid pier parts, and the slope ratio of the inner and outer walls of the transverse bridge is 1:80.
[0019] Lay out the 2.5m-high formwork on the top of the platform, and pour the 2.5m-high solid section at the bottom of the pier; the solid section formwork will not be dismantled after the concrete is poured, and the stiff skeleton will be used to position and bind the steel bars of the pier body, and use a crane to place it on the top of the solid section formwork Install and support the 4.5m-high inner and outer formwork of Sections 1 and 2, pour the pier body concret...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More