Construction method for continuously prefabricating section bodies of tube sections of immersed tube of dry dock
A construction method and segment technology, which are applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve the problem of complex reciprocating movement of steel bar binding platforms and formwork trolleys, inability to achieve continuous construction of adjacent pipe segments, and chiseling. , cleaning, rust removal and other problems are difficult to achieve the effect of facilitating the construction of separate warehouses, easy control of template displacement, and reducing the impact of surrounding environmental conditions
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0065] The invention provides a construction method for continuous prefabrication of immersed pipe sections in dry dock, which includes the following steps:
[0066] Step 1. According to the plane size and spatial position of the dry dock and the immersed tube section, divide the immersed tube section into several sections, and number them sequentially as No. 1 section, No. 2 section, No. 3 section, and No. 4 section. No. segment... to form the number of continuous flow construction compartments;
[0067] Step 2, such as Figure 1~2 As shown, the No. 1 segment is bound with the bottom plate reinforcement.
[0068] Step 3, if Figure 3-4 As shown in Fig. 1, section 1 shall be erected and bound with reinforcement platform 1 for the partition wall, and at the same time, section 2 shall be bound with bottom plate reinforcement;
[0069] Step 4, such as Figure 5-6 As shown in Fig. 1, the roof reinforcement binding platform 4 is erected and bound for the No. 1 section, while th...