Decision-making method, device and system for optimal power generation control based on coordination between two time points
A technology for power generation control, coordination and optimization, applied in the direction of single-grid parallel feeding arrangement, etc., can solve the problems of complex safety and stability characteristics, increase of random factors, and insufficient flexible adjustment of power supply, etc., to meet decision-making accuracy, ensure real-time performance, and overcome calculation. huge amount of effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0052] The embodiment of the present invention provides a decision-making method for coordinating and optimizing power generation control based on two time points, where the current operating time of the power grid is set as t 0 , the current operating state of the grid is S 0 , the real-time power generation control period is T, and the set of power plants that perform real-time power generation control according to the optimization decision of the control center is A;
[0053] like figure 1 As shown, the method specifically includes the following steps:
[0054] S1, obtain the active power injected into the power grid by each power plant, load, AC side node of the DC system and external liaison nodes in the power grid under the jurisdiction of the control center to the power transmission equipment and the active power of the stable section that the control center is responsible for overload monitoring; In the embodiment of the present invention In a specific embodiment, th...
Embodiment 2
[0096] Based on the same inventive concept as Embodiment 1, an embodiment of the present invention provides a decision-making device for coordinating and optimizing power generation control based on two time points, including:
[0097] Diversity module to obtain t 0 The initial value of the active power control command of each power plant at time A at +T, t 0 The initial value of the active power control command of each power plant in A at time +2T and the corresponding active power control command optimization decision-making equation, the set of power plants that meet the requirements of active power regulation speed is recorded as B, and the power plant t in B is denoted as B. 0 +T time, t 0 The initial value of the active power control command at time +2T is taken as the corresponding power plant t 0 +T time, t 0 The final value of the active power control command at time +2T, the set of power plants in A except the power plants in B is denoted as C; where, t 0 Represe...
Embodiment 3
[0104] Based on the same inventive concept as Embodiment 1, an embodiment of the present invention provides a decision-making system for coordinating and optimizing power generation control based on two time points, including:
[0105] a processor adapted to implement the instructions; and
[0106] The storage device is adapted to store a plurality of instructions, the instructions are adapted to be loaded by the processor and perform the steps described in any one of Embodiment 1.
[0107] As will be appreciated by those skilled in the art, the embodiments of the present application may be provided as a method, a system, or a computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (includi...