Device and method for monitoring vault settlement in tunnel construction
A technology for vault settlement and tunnel construction, which is applied in measuring devices, surveying and navigation, and electrical devices, etc., can solve problems such as inaccurate initial data, achieve convenient operation, simple data collection methods, and ensure construction safety.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0054] Specifically, such as figure 2 and image 3 As shown, a tunnel construction vault settlement monitoring device includes an inclinometer sensor 2-4, an inclinometer sensor wire 2-5, an inclinometer tube wire channel 2-6, an inclinometer tube 2-7 and a monitor. Wherein, the electric wire 2-5 of described inclinometer sensor is placed in electric wire channel 2-6, and the terminal 2-8 of described inclinometer sensor electric wire 2-5 is connected with the connection electric wire 3-8 in monitor, and is done well Waterproof treatment.
[0055] refer to image 3 As shown, the monitor is equipped with a USB interface, a jack and a built-in lithium battery, the jack 3-7 is connected with the connecting wire 3-8 with a plug, and the USB interface 3-5 can be connected with a computer for recording and storing data.
[0056] A power switch 3-4, a function button 3-6, an adjustment knob 3-3 and a display screen 3-2 are installed on the monitor.
[0057] There are 3 copper wi...
Embodiment 2
[0078] This implementation also provides a method for monitoring tunnel construction vault settlement using the above-mentioned device, including the following steps:
[0079] A. Use a drilling rig to drill holes forward above the excavation face to place the inclinometer tube 2-7; preferably, the inclinometer tube is 20m long, and further, the inclinometer tube wall is provided with Wire channel.
[0080] B. Set a sensor placement groove every 1m, install 20 inclinometer sensors 2-4 in the corresponding placement grooves of the inclinometer tube 2-7 respectively, and the inclinometer sensor and the inclinometer tube are tightly fixed;
[0081] C. The electric wires 2-5 of each inclinometer sensor are placed in the electric wire channel 2-6 of the corresponding inclinometer pipe wall;
[0082] D. Place the inclinometer tube equipped with the inclinometer sensor in the pre-drilled borehole, and place the tube mouth "positively and negatively", and place the sensor wire termina...