A construction method and slot-type technology, which is applied in the field preparation of formwork/formwork/work frame, building components, construction, etc., can solve the problems of grout leakage, manual grinding, time-consuming and labor-intensive, etc., to ensure vertical degree, guarantee the construction quality and improve the installation efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0037] like Figure 1 to Figure 8 As shown in the figure, a kind of anti-spill grooved cylindrical formwork includes two arc-shaped formworks 1, and the two ends of the two arc-shaped formworks 1 are welded and fixed with first connectors 2, and the first connectors 2 are provided with There is a first connecting hole 3, and the upper and lower arc-shaped templates 1 are assembled by using the first connecting hole 3 on the first connecting piece 2 and connecting bolts, and the outer walls of the two arc-shaped templates 1 are fixedly connected with Rib plate 5 and connecting steel plate 6, connecting steel plate 6 is arranged in the circumferential direction, connecting steel plate 6 is a crescent-shaped structure with narrow ends and wide middle, the middle part of connecting steel plate 6 is fixedly connected with reinforcing rod 16, and the outer side of reinforcing rod 16 is sleeved There are pull rings 17 . Since the stress in the middle of the arc-shaped formwork 1 is ...
Embodiment 2
[0043] like Figure 9 As shown, a construction method of anti-overflow grout slot type cylindrical formwork includes the following steps:
[0044] Step 1. Preparatory work: pour concrete base and pre-embed bolts (to provide convenience for the installation of the cylindrical formwork on the bottom floor), bind the column reinforcement of the designed column and complete the acceptance, and install the fixed pulley 21 in the surrounding area of the designed column Hoist 22 and fixed rod 23;
[0045] Step 2. Assembling the arc-shaped formwork 1: use the positioning piece 13 to insert into the positioning groove 9, and at the same time ensure the cooperation of the flow blocking groove 10 and the flow blocking piece 14, so as to realize rapid assembly, and move the positioning piece 13 to the hook and the second connecting piece 7 Snapping prevents deviation when connecting the second connecting piece 7 and the third connecting piece 11, and the connecting portion 151 of the f...