A mass concrete and concrete technology, applied in bridges, bridge parts, bridge materials, etc., can solve the problems of complex spatial special-shaped structure, poor maintenance effect, pier column quality and appearance influence, etc., to avoid concrete segregation and improve pouring quality. , the effect of eliminating the phenomenon of slurry leakage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0043] Such as Figure 1-10 As shown, a kind of special-shaped bridge pier column mass concrete pouring process with slope at both ends, the W-shaped beam pier column is taken as an example below, which includes the following steps:
[0044] S1. Foundation pouring: construct according to the construction drawing and pour the pier column foundation 10 as the cap, and the pre-embedded steel plate 40 pre-embedded in the foundation 10 is used as the fixing of the Bailey sheet column 50, and the top surface of the pre-embedded steel plate 40 is connected to the foundation 10 The top surface is flat; after the pouring of foundation 10 is completed, carry out foundation treatment on the necessary site for formwork reinforcement on the outside of the foundation, first use plain soil to backfill and compact to a distance of about 1 meter from the top surface of the foundation, and then use 6% lime soil above the plain soil 20 Lay and compact to a distance of 0.3-0.4 meters from the top...