Post-grouting bored pile construction method
A technology of bored piles and construction methods, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve the problems that concrete prefabricated piles are difficult to pass through hard silty clay layers, and achieve large bearing capacity and ensure mud Effects on mass, avoidance of collapse and diameter reduction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0050] Post-grouting bored pile construction method steps of the present invention are as follows:
[0051] A post-grouting bored pile construction method is characterized in that it comprises the following steps:
[0052] Construction preparation:
[0053] 1) According to the physical characteristics of the construction site soil, select appropriate mechanical equipment such as drilling rigs, drill bits, arm guard casings, etc.;
[0054] 2) Concrete is made of dense sand and gravel, and the cement used for post-grouting is PC32.5 ordinary Portland cement, and the water-cement ratio is 1:2;
[0055] 3) Selection of steel bars and welding rods, the steel bars are φ-HPB300, φ-HRB335, φ-HRB400 grades; Among them: HPB300 steel bars use E43 welding rods, HRB335 and HRB400 steel bars use E50 type welding rods;
[0056] Specific construction steps:
[0057] A. Hole forming
[0058] 1) Positioning and setting out: Use the wire method to measure and place the axis with the total st...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com