Fabricated karst grouting pipe protecting assembly and grouting method
A prefabricated, tube component technology, applied in soil protection, roads, construction, etc., can solve the problems of increasing the difficulty of hole cleaning, failure to increase pressure, and loss of grout, so as to enhance the effect of grouting reinforcement, reduce loss, reduce The effect of the loss of slurry
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] This embodiment provides an assembled karst grouting protection pipe assembly;
[0036] Such as Figure 1-Figure 6 As shown, the assembled karst grouting protection pipe assembly in this embodiment includes multiple joints of protection pipes 11 that are detachable in sequence. The protection pipes 11 are hollow and have a certain thickness. Each section of the protection pipe 11 is provided with multiple A grouting hole 13, the grouting hole 13 communicates with the inside and outside of the protective pipe 11, a check valve plate 33 is arranged in the grouting hole 13, and the one-way valve plate 33 can make the grout in the protective pipe 11 flow from The grouting hole 13 flows out and prevents the external grout from flowing into the protective tube 11 from the grouting hole 13 .
[0037] In the present invention, multiple protective pipes are detachably butted in sequence, and each protective pipe is provided with a plurality of grouting holes. , the one-way val...
Embodiment 2
[0047] Such as Figure 1-Figure 6 As shown, this embodiment provides a grouting method using the assembled karst grouting protection pipe assembly in Embodiment 1, including the following steps:
[0048] Step 1. According to the pile position control coordinates, drill holes on the ground;
[0049] Step 2. After the drilling is completed, put a model tube with the same outer diameter as the protective tube in the borehole. The model tube is required to be placed in the center of the borehole as much as possible, and the casing material 43 is used to fill the space between the model tube and the borehole wall. When filling the casing material, reserve a section at the opening of the drill hole without filling (cement mortar will be injected later), take out the model tube after the casing material is solidified, and then put the first section of protective tube into the drill hole , before the first section of protective tube is put in, connect the second section of protective...