System for Quantitative Calculation of Concrete Filling Voids During Tunnel Secondary Lining Construction

A secondary lining and quantitative calculation technology, applied in tunnel lining, tunnel, shaft lining, etc., can solve problems such as unclear concrete pouring status, achieve reliable judgment basis, avoid voids, and ensure the effect of construction quality

Active Publication Date: 2021-09-24
RAILWAY ENG RES INST CHINA ACADEMY OF RAILWAY SCI +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] One of the technical problems to be solved by the present invention is to provide a solution, which provides a system for quantitatively judging the pouring state of lining concrete during the construction period, effectively solving the problem of unclear concrete pouring state during the secondary lining construction period Problems can provide reliable judgment basis for construction personnel, ensure the quality of lining construction, and reduce or avoid the formation of voids from the source

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • System for Quantitative Calculation of Concrete Filling Voids During Tunnel Secondary Lining Construction
  • System for Quantitative Calculation of Concrete Filling Voids During Tunnel Secondary Lining Construction
  • System for Quantitative Calculation of Concrete Filling Voids During Tunnel Secondary Lining Construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0027] The implementation of the present invention will be described in detail below in conjunction with the accompanying drawings and examples, so as to fully understand and implement the implementation process of how to apply technical means to solve technical problems and achieve corresponding technical effects in the present invention. The embodiments of the present application and the various features in the embodiments can be combined with each other under the premise of no conflict, and the formed technical solutions are all within the protection scope of the present invention.

[0028] Additionally, the steps shown in the flowcharts of the figures may be performed in a computer system, such as a set of computer-executable instructions. Also, although a logical order is shown in the flowcharts, in some cases the steps shown or described may be performed in an order different from that shown or described herein.

[0029] Image 6 It is a schematic structural diagram of ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a system for quantitatively calculating concrete pouring voids during the secondary lining construction period of tunnels. The system includes: a plurality of detection units, each detection unit detects the height of the concrete pouring surface, and generates a pouring height representing the concrete The electrical signal; the judgment unit, which receives multiple electrical signal data, and processes each electrical signal data to obtain the height data of the monitoring points distributed according to a certain density on the concrete pouring surface during the secondary lining construction period, and according to these heights data to calculate the volume of unfilled voids above the concrete surface and below the flashing. The invention effectively solves the problem of unclear pouring state of the concrete during the secondary lining construction period, can provide reliable judgment basis for construction personnel, guarantee the quality of lining construction, and reduce or avoid the formation of cavities from the source.

Description

technical field [0001] The invention belongs to the technical field of tunnel construction, and relates to a system for quantitatively calculating the concrete pouring cavity during the secondary lining construction period of the tunnel. Background technique [0002] Holes in the tunnel lining will not only cause the vault to fall off, threatening driving safety, but also reduce the bearing capacity of the tunnel structure and reduce the engineering safety factor. Since the lining concrete was poured in the formwork trolley during the secondary lining construction, the construction personnel could not accurately judge the pouring state of the vault concrete, which resulted in the insufficiency of the lining concrete pouring during the secondary lining construction and could not be dealt with in time. However, the existing detection and monitoring technology cannot effectively identify the pouring state of the lining concrete during this construction period, so the insufficie...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E21F17/18E21D11/10
CPCE21D11/10E21F17/18
Inventor 马伟斌韩自力叶阳升安哲立郭小雄王勇刘艳青马荣田刘延宏付兵先邹文浩程爱君牛亚彬
Owner RAILWAY ENG RES INST CHINA ACADEMY OF RAILWAY SCI
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products