A technology of underground diaphragm wall and assembly method, applied in sheet pile wall, construction, infrastructure engineering and other directions, can solve problems such as uncontrollable pouring quality, and achieve the effect of improving construction efficiency and improving connection tightness.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0048] The specific embodiments of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments. The following examples are intended to illustrate the present invention, but not to limit the scope of the present invention.
[0049] combine Figure 1 to Figure 18 As shown, a method for assembling a prefabricated diaphragm wall of the present invention is schematically shown, wherein the first diaphragm wall component 3 is a regular trapezoid structure, and the second diaphragm diaphragm wall component 5 is an inverted trapezoid structure, such as Figure 1 to Figure 10 , the assembly method includes the following steps:
[0050] Step S1 , using a groove forming machine to construct a first groove 1 on the ground, and setting a positioning mechanism 2 at the opening of the first groove 1 .
[0051]Step S2, hoisting the first underground continuous wall assembly 3 into the first groove 1, specifically: hoisting the ...