Construction method for connecting new sewage pipes to existing sewage pipes
A construction method and sewage pipe technology, applied in the direction of sewage discharge, sewer pipe system, construction, etc., can solve the problems of large one-time investment, bursting of airbags, flooding, etc., to ensure the construction period, overcome repeated blockage, and reduce safety risk effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0036] The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.
[0037] Such as Figure 3 to Figure 10 As shown, the construction method for connecting new sewage pipes and existing sewage pipes in this embodiment includes the following steps:
[0038] S1, new connection transition well: build a connection transition well 5 outside the existing sewage well 1, the connection transition well 5 is separated from the existing sewage well 1 by a certain distance, and the connection transition well 5 faces the existing sewage well A door opening 51 is reserved on the wall of 1, and the new sewage pipe 4 is connected to the transition well 5;
[0039] S2. Reinforcement of inter-well soil: grouting and reinforcement of the inter-well soil 6 between the connecting transition well 5 and the existing sewage well 1;
[0040] S3. Horizontal excavation of steel pipe casing: insert the steel casing 7 with grout...
PUM