A kind of electric engineering pipeline and its construction method
A power engineering and pipeline technology, applied in the field of power engineering, can solve problems such as inconvenience of operation, and achieve the effects of convenient operation, tight connection and stable installation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0051] refer to figure 1 , Embodiment 1 of the present invention provides a power engineering pipeline, including a first tube 1, a second tube 2, a first pipe block 3 and a second pipe block 4, the first pipe block 3 and the second pipe block 4 are respectively Slidingly connected in the first tube 1 and the second tube 2, one end of the first tube 3 and the second tube 4 are respectively limited in the first tube 1 and the second tube 2, so that the first tube 3. The second tube block 4 cannot be separated from the first tube 1 and the second tube 2. When the first tube 3 and the second tube 4 slide to the ends of the first tube 1 and the second tube 2 respectively, When it is in the upper position, the first pipe block 3 and the second pipe block 4 are inserted and fitted. At this time, the first tube 1, the second tube 2, the first tube block 3 and the second tube block 4 form a cylindrical shape, the bottom of the pipeline is fixed with a base 22, the base 22 is elongate...
Embodiment 2
[0070] Embodiment 2 of the present invention provides a construction method for power engineering pipelines, comprising the following steps,
[0071] Excavation of foundation trench: Excavation of foundation trench in the construction area;
[0072] Pipe installation: slide the first pipe block 3 and the second pipe block 4, make the tenon 5 of the first pipe block 3 and the tenon groove 6 of the second pipe block 4 fit together, and install the first stopper 7 and the second stopper Block 10 and the third block 13, to complete the assembly of a single pipeline, and then arrange several pipelines in the base groove and connect them as a whole;
[0073] Block the nozzle of the pipe: check the cable through the pipe to prevent blockage, and block the openings at both ends of the pipe to prevent debris from entering;
[0074] Backfill foundation trench: Backfill soft soil around the pipeline to achieve the compactness specified in the design to complete the construction.