A high ground stress and initial support technology, applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve the problem of rockburst damage to initial support, large deformation cannot be accurately estimated, and reserved deformation cannot meet requirements, etc. problems, to achieve the effect of ensuring safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0044] Such as figure 1 , 2 , 3, 4, and 6, the present invention provides a tunnel initial support construction method that can adapt to high ground stress and rockburst, mainly comprising the following steps:
[0045] (1) Since high ground stress and rockburst are always accompanied by large deformation and encroachment of surrounding rock and primary support, when determining the design scheme, the constructed primary support fully takes into Leave room for deformation;
[0046] (2) In order to release the surrounding rock deformation caused by high ground stress and rockburst, the reserved space is filled with omega-shaped thin steel plates. The form of omega-shaped thin steel plates is as follows Figure 5 As shown; when the stress release of the surrounding rock causes large deformation, the omega-shaped thin steel plate can adapt to the large deformation of the surrounding rock through its own compression deformation and ensure the stability of the steel arch; when the...