Vertical jacking construction method for tunnel inclined shaft entering main tunnel

A construction method, the technology of the front hole, applied in the direction of tunnels, tunnel linings, shaft linings, etc., can solve the problems of large consumption of temporary supports, difficulty in removing slag, and narrow construction work surface, so as to reduce the amount of temporary supports and the jacking steps Clear, clear, simple assembly and stress effects

Active Publication Date: 2021-02-02
CCCC TUNNEL ENG +1
View PDF5 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003]1. The form of straight-line climbing guide tunnel (such as "big bag method"). The problems of this kind of method are: ①The main part of the connecting part of the inclined shaft entering the main tunnel Tunnels and sub-holes require a large amount of excavation; ②The excavation part of the tunnel is concentrated on the vault, and it is inconvenient to pour concrete backfill; ③The part of the tunnel expansion needs to be backfilled with a large amount of concrete, which will generate excess load on the support structure ;
[0004]2. Curved climbing guide tunnel form (such as "arc guide pit method"). The disadvantages of this type of method are: ①The curved climbing route increases the surveying and mapping ②The construction work surface at the junction of the pilot tunnel and the main tunnel is narrow, and large tools cannot be used; ③Curved slopes have high requirements for the protection of surrounding rocks, requiring multi-step ascending excavations, and the construction process takes a long time to change. It was sealed by shotcrete in time, and the surrounding rock was severely weathered;
[0005]3. The construction method of turning the small pilot tunnel to the roof. The disadvantages of this method are: ① There is a long turning section after the pilot tunnel enters the main tunnel, and this section consumes A large number of temporary supports (because they need to be removed in the subsequent excavation process); ② The steering position of the pilot tunnel needs to be reasonably arranged to turn to the temporary supports, which requires high technical requirements for the erection and reinforcement of the temporary supports; The large-span excavation surface is generated by the three-dimensional suspended force-bearing area, and the safety is poor;
[0006]4. Similar to the CRD method of expanding the excavation into the main hole, the disadvantages of this method are: ①The cross brace affects the excavation operation, and it is difficult to remove the ballast; ②The construction step There are many and complex procedures, and the construction period is long; ③ Higher technical requirements

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Vertical jacking construction method for tunnel inclined shaft entering main tunnel
  • Vertical jacking construction method for tunnel inclined shaft entering main tunnel
  • Vertical jacking construction method for tunnel inclined shaft entering main tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0045] Taking the working condition below as an example of 6.3m x 5m inclined shaft 1 excavating into a 6.3m x 9.0m normal tunnel with a width x height of 6.3m x 9.0m, the vertical roof of the tunnel inclined shaft of the present invention will be described in conjunction with the accompanying drawings. liter construction method for further description, the construction method includes the following steps:

[0046] Step 1: Excavate the inclined shaft: Firstly, excavate the inclined shaft 1 to a distance of ten meters from the side wall I3 of the main tunnel 2 according to the common excavation method. The subsurface shall be treated with shotcrete sealing, and if necessary, grouting bolts shall be installed for reinforcement; then a rectangular pilot tunnel 4 shall be excavated until the side wall II 5 of the main tunnel. The height of the rectangular pilot tunnel is 2.75 meters lower than the height of the vault of the inclined shaft. With the excavation progress, the tempora...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to the technical field of construction, and discloses a vertical jacking construction method for a tunnel inclined shaft entering a main tunnel. The method comprises the following steps that step one, a rectangular pilot tunnel is excavated when the inclined shaft is excavated to a certain distance away from the main tunnel; step two, a cuboid support is built in the rectangular pilot tunnel within the range of the main tunnel; step three, an arched support is built; and in the later step, excavation of a vault of the whole main tunnel part is completed through cyclic transposition jacking of two sets of jacks while excavation is conducted, and meanwhile independent supporting for the vault of the main tunnel is formed. According to the vertical jacking excavation method, traditional construction processes such as pilot tunnel climbing are abandoned, another path is found, main horizontal excavation is changed into main vertical excavation, the temporary supporting amount is reduced, and waste is avoided; and after excavation, a surrounding rock area of a three-fork joint section can be reserved, the expanding excavation problem is basically avoided, and large-mass concrete backfilling and large-scale use of complex supporting structures are also avoided.

Description

technical field [0001] The invention relates to the field of construction technology, in particular to a vertical jacking construction method for a tunnel inclined shaft entering a main tunnel. Background technique [0002] Common construction methods for inclined shafts entering main tunnels are as follows: [0003] 1. Straight-line climbing guide tunnel form (such as "big bag method"). The problems of this type of method are: ①The main hole and the secondary hole at the junction of the inclined shaft and the main hole require a large amount of excavation; ②Tunnel expansion The excavation part is concentrated on the vault, and it is inconvenient to pour concrete backfill; ③The excavation part of the tunnel needs to be backfilled with a large amount of concrete, which will generate excess load on the support structure; [0004] 2. Curved climbing guide tunnel form (such as "arc guide pit method"). The disadvantages of this type of method are: ①The curved climbing route incr...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D11/10E21D11/18
CPCE21D11/10E21D11/102E21D11/105E21D11/107E21D11/18Y02E10/20
Inventor 何鹏飞孙兴亮康飞张超赵智郭大亮
Owner CCCC TUNNEL ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products