Continuous beam No.0 block reinforced concrete-filled steel tube support erecting and dismantling method
A technology of steel pipe concrete and concrete, which is applied in the field of bridge construction, and can solve the problems of self-heavy installation and dismantling, self-heaviness, troubles, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0023] Step 1. Measurement and setting-out: The measurement and setting-out personnel should conduct detailed technical disclosure for inspection, and then use the measurement and setting-out tool to perform measurement and setting-out at the designated position. fix.
[0024] Step 2. Leveling and brushing the isolation layer: After determining the position, manually use concrete to level the position supported by the cap, and after leveling, manually brush the isolation layer at the erected position.
[0025] Step 3. Install the steel pipe: After installing the first section of 180cm steel pipe, pour plain concrete inside the steel pipe. After the final setting, install the 20cm high steel pipe and pour sulfur mortar. The resistance wire is buried in the sulfur mortar. The 180cm steel pipe and the 20cm high steel pipe are used as the One group, follow this procedure to install from bottom to top, the steel pipe concrete is built to the bottom of the beam of No. Steel pipe wi...