A rapid judgment method for maintenance timing of drained asphalt pavement
A drainage asphalt, determination method technology, applied in the direction of radiation pyrometry, roads, roads, etc., can solve the problems of blocked road surface structure, road surface pollution, long detection time, etc., achieve significant economic and social benefits, reduce The influence of road traffic and the effect of making operation errors difficult
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0047] Such as figure 1 As shown, the present embodiment provides a method for quickly determining the maintenance timing of drained asphalt pavement, including:
[0048] S1: Select the target experimental road;
[0049] S2: setting road markings on the target experimental road;
[0050] S3: Use an infrared temperature detection instrument to detect the ambient temperature before opening to traffic at the marked place on the road surface and the ground temperature of the drained asphalt pavement before opening to traffic;
[0051] S4: Construct a first curve according to the ambient temperature before opening to traffic and the ground temperature of the drainage asphalt pavement before opening to traffic;
[0052]S5: Measure the ambient temperature after opening to traffic and the ground temperature of the drained asphalt pavement after opening to traffic at the marked place on the road surface after opening to traffic;
[0053] S6: Construct a second curve according to the...
Embodiment 2
[0060] Such as figure 2 As shown, the present embodiment provides a method for quickly determining the maintenance timing of drained asphalt pavement, including:
[0061] S1: Select the target experimental road;
[0062] S2: setting road markings on the target experimental road;
[0063] Preferably, 2-4 road surface markings are selected at regular intervals on the target experimental road, and the road surface markings are distributed on the non-wheelmarks of each lane of the target experimental road. There are multiple road surface labels, and each road surface label corresponds to one of the second curves;
[0064] Just like the method of taking the average value of multi-point measurement in the traditional technology, in this embodiment, the method of multi-point measurement is also used, and the influence of chance on the measurement can be reduced through multi-point measurement.
[0065] S3: Use an infrared temperature detection instrument to detect the ambient tem...
Embodiment 3
[0076] This embodiment provides a method for quickly judging the timing of drainage asphalt pavement maintenance, including:
[0077] S1: Select the target experimental road;
[0078] S2: setting road markings on the target experimental road;
[0079] S3: Use an infrared temperature detection instrument to detect the ambient temperature before opening to traffic at the marked place on the road surface and the ground temperature of the drained asphalt pavement before opening to traffic;
[0080] S4: Construct a first curve according to the ambient temperature before opening to traffic and the ground temperature of the drainage asphalt pavement before opening to traffic;
[0081] S5: Measure the ambient temperature after opening to traffic and the ground temperature of the drained asphalt pavement after opening to traffic at the marked place on the road surface after opening to traffic;
[0082] S6: Construct a second curve according to the ambient temperature after opening to...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com