Novel flange manufacturing process
A manufacturing process and flange technology, which is applied in the field of new flange manufacturing process, can solve problems such as easy cracks or breaks, reduced service life of flanges, and uneven force on forgings, so as to enhance its own strength and service life. , the effect of uniform force
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0035] A manufacturing process of a novel flange, comprising the following steps:
[0036] A: Select a steel plate with a thickness of 80mm as a spare, check the surface of the material, and it is not suitable to use the steel plate with serious corrosion, heavy skin, cracks and other defects;
[0037] B: Lift the vertically erected steel plate forgings into the upsetting equipment consisting of upsetting dies and rotary worktables with a hoist, fix the forgings on the rotary worktable, and use a 5000T hydraulic press to upset the forgings. During the process, the worktable is rotated until the entire surface of the forging is upset, so as to ensure that the forging is upset into a circle;
[0038] C: Forging the forgings obtained in step B, the forging is divided into two stages, the first stage is forging temperature 900°C, forging time is 18s, the second stage is forging temperature is 925°C, forging time is 15s, after the forging is completed Cooling, the cooling temperat...
Embodiment 2
[0048] A manufacturing process of a novel flange, comprising the following steps:
[0049] A: Select a steel plate with a thickness of 100mm as a spare, check the surface of the material, and it is not suitable to use the steel plate with defects such as severe corrosion, heavy skin, and cracks;
[0050] B: Lift the vertically erected steel plate forgings into the upsetting equipment consisting of upsetting dies and rotary worktables with a hoist, fix the forgings on the rotary worktable, and use a 5000T hydraulic press to upset the forgings. During the process, the worktable is rotated until the entire surface of the forging is upset, so as to ensure that the forging is upset into a circle;
[0051] C: Forging the forgings obtained in step B, the forging is divided into two stages, the first stage is forging temperature 915°C, forging time is 20s, the second stage is forging temperature is 930°C, forging time is 18s, after the forging is completed Cooling, the cooling temper...
Embodiment 3
[0061] A manufacturing process of a novel flange, comprising the following steps:
[0062] A: Select a steel plate with a thickness of 110mm as a spare, check the surface of the material, and it is not suitable to use the steel plate with serious corrosion, heavy skin, cracks and other defects;
[0063] B: Lift the vertically erected steel plate forgings into the upsetting equipment consisting of upsetting dies and rotary worktables with a hoist, fix the forgings on the rotary worktable, and use a 5000T hydraulic press to upset the forgings. During the process, the worktable is rotated until the entire surface of the forging is upset, so as to ensure that the forging is upset into a circle;
[0064] C: Forging the forgings obtained in step B. The forging is divided into two stages. The forging temperature of the first stage is 930°C and the forging time is 23s. The forging temperature of the second stage is 935°C and the forging time is 20s. After the forging is completed Coo...
PUM
| Property | Measurement | Unit |
|---|---|---|
| Thickness | aaaaa | aaaaa |
| Thickness | aaaaa | aaaaa |