Pre-control method for structural deformation of super high-rise building
A building structure and pre-control technology, which is applied in the field of building construction quality control, can solve the problems of not considering the vertical deformation and differential deformation rules of super high-rise buildings, and achieve the effects of reducing calculation running time, avoiding inoperability, and reducing errors
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] The technical scheme of the pre-control method of a kind of super high-rise building structural deformation of the present embodiment is as follows:
[0050] A kind of pre-control method of deformation of super high-rise building structure, comprises the steps:
[0051] S1, setting the pilot leveling position during the construction of the building structure;
[0052] S2. Carry out simulation analysis on the construction process of the superstructure of the building structure, and perform the first compensation for the vertical deformation of the building structure at each of the pilot leveling positions, to obtain a load model of the superstructure.
[0053] The method for pre-controlling the structural deformation of a super high-rise building in this embodiment takes into account the leveling during the construction process during the simulation analysis, so that the compensation value of the vertical deformation is closer to the actual situation.
[0054] As a bett...